REHABILITATION OF LANDS, O. Reg. 35/24

Schedule 2

Cite as REHABILITATION OF LANDS, O. Reg. 35/24, Schedule 2 · current to November 11, 2026 · consolidated from April 1, 2024 · read from e-Laws on November 16, 2026

The text

Schedule 2 CONTENTS OF CLOSURE PLANS A closure plan shall contain the following information: 1. Letter of transmittal: i. The signature of the following individual, and the date on which the letter was signed: A. The proponent, if the proponent is an individual. B. If the proponent is a corporation, a senior officer of the corporation. ii. A statement that the submitted closure plan constitutes the entire closure plan under Part VII of the Act. iii. The names of any agents or employees authorized to act on the proponent’s behalf. 2. Certificates: i. Proponent’s certificate: A. If the closure plan meets the requirements of this Regulation, a certificate in Form 1 to this Schedule, in English or in French, signed by the individual or individuals specified in sub-subparagraph C. B. If the closure plan does not meet the requirements of this Regulation and is being submitted together with a conditional filing order, a certificate in Form 2 to this Schedule, in English or in French, signed by the individual or individuals specified in sub-subparagraph C. C. The certificate shall be signed by, 1. the proponent, if the proponent is an individual, or 2. if the proponent is a corporation, two senior officers, one of whom must be the chief financial officer or, if the corporation does not have a chief financial officer, an individual who performs a similar function in the corporation. ii. Qualified person certificates: A. For each Part of the Code, the certificate specified by sub-subparagraph B, C or D, as applicable, signed by a qualified person in accordance with the following rules: 1. Parts 1 to 4, 6, 8 and 10 may only be signed by a professional engineer under the Professional Engineers Act or a member of the Association of Professional Geoscientists of Ontario. 2. Part 7 may only be signed by a professional engineer under the Professional Engineers Act or a member of the Association of Professional Geoscientists of Ontario or the Ontario Institute of Professional Agrologists. 3. Parts 5 and 9 may be signed by any qualified person. B. If the rehabilitation measures set out in the closure plan conform to the standards, procedures and requirements of the Part or Parts of the Code to which the certificate relates, the certificate shall be in Form 3 to this Schedule. C. If the rehabilitation measures set out in the closure plan do not conform to the standards, procedures, and requirements of the Part or Parts of the Code to which the certificate relates, but the non-conformance is only to the extent permitted by a conditional filing order submitted together with the closure plan, the certificate shall be in Form 4 to this Schedule. D. If the certificate is for the purposes of subsection 4 (3) of this Regulation, the certificate shall be in Form 4 to this Schedule. E. A form required by this paragraph shall include the qualified person’s name and, if the qualified person is a professional engineer under the Professional Engineers Act or a member of the Association of Professional Geoscientists of Ontario, The Ontario Association of Landscape Architects or the Ontario Institute of Professional Agrologists, the person’s designation. 3. Project information: i. The proponent’s name and address and the location and address of the project site. ii. The boundaries of the project site and details of the land tenure of the project, including the proponent’s interest in the mining lands within the boundaries and of the tenure of land not owned but leased or otherwise controlled by the proponent. iii. A site plan of legible scale indicating the location of all project features, including all openings to the surface, in relation to the site boundaries and the claim numbers, parcel numbers and, where applicable, the township name, lot number and concession number. iv. Plans and sections of proposed new underground or open pit development. 4. Current project site conditions: i. Details of the current land use of the site and the immediately adjacent lands that may be affected by the project, including current zoning and official plan designations, where applicable. ii. Topographical details of the site, including a plan of appropriate scale and contour interval where the project will alter existing site topography. iii. Details of the surface waters on or flowing through the site and any surface waters receiving flow from the site, including an assessment of the quality and quantity of such waters that indicates whether and to what extent they will be affected by the project and shall be consistent with the monitoring requirements specified in the Code and a plan of legible scale showing the current location of all such waters and their watershed boundaries. iv. Details of the ground waters within and beyond the site boundaries that may be affected by the project, including the identification of aquifers and an assessment of the quality and quantity of such ground waters that indicates whether and to what extent they will be affected by the project and shall be provided in accordance with the Code. v. Details of the terrestrial plant and animal life that may be affected by the project. vi. Details of the aquatic plant and animal life that have been or may be affected by the project. vii. Complete details of any previous activities that may have resulted in a mine hazard existing on the site or any contamination of the site that has occurred, including the history of the site, an assessment of any physical mine hazards that exist and an assessment of any current contamination of soils, surface and ground waters that exist at the start of the project. 5. Project description: i. A brief summary of the project. ii. Details of the mineralogy of the ore and host rock within the site. iii. Details of the mining activities anticipated throughout the life of the project, including methods and rates of mine development and mining, and methods and procedures for handling mine backfill. iv. Details of any processing, including a general description of the process, types and rates of any reagents used and a process water balance. v. Details of existing and expected buildings and infrastructure on the site, including their size, type, use and location and a surface plan, at a legible scale, showing their location. vi. Details of the production, handling and disposal of any tailings on the site, including the physical and chemical nature of the tailings, an assessment of the potential for metal leaching and acid mine drainage in accordance with the Code, the rate of production of tailings, methods of handling tailings, the location, size and nature of any tailings impoundment and treatment areas and a surface plan of legible scale showing the location of any such areas with engineering details of any impoundment structures. vii. Details of the production, handling, storage and disposal of waste rock, ore, concentrate and overburden, including the physical and chemical nature of the materials, an assessment of the potential for metal leaching and acid mine drainage in accordance with the Code, the rates of production of such material, methods of handling and the location, size and nature of any storage or disposal areas and a surface plan of legible scale showing the location of any storage or disposal areas. viii. Available details of any existing or proposed waste management systems and treatment or disposal sites, including disposal sites located within tailings areas, a description of the treatment or disposal process or system and a surface plan of legible scale showing the location of any treatment or disposal site and effluent discharge points. ix. Details of any water management or treatment systems, including a description of the processes and physical facilities for such systems. x. Details of storage sites for petroleum products, chemicals, explosives, hazardous substances and toxic substances, including the quantity of materials stored, the size, nature and location of such storage areas and a surface plan of legible scale showing their location. xi. A proposed schedule for the project. xii. If a management plan for materials that produce or may produce acid rock drainage or metal leaching is required under the Code, a copy of the management plan. 6. Progressive rehabilitation: details of any such measures anticipated during the life of the project, including a schedule for carrying them out. 7. Rehabilitation measures — temporary suspension: i. Details of measures to, A. restrict access to the project site, buildings and other structures to authorized persons, B. secure petroleum products, chemicals, waste and waste management systems, and C. dispose of or remove explosives from the site. ii. Details of measures for the prevention of unauthorized or inadvertent access to mine openings to the surface. iii. Details of measures to ensure maintenance of mechanical and hydraulic systems in a no-load condition and protect electrical systems from unauthorized or inadvertent access. iv. Details of measures to control effluents of all types. v. Details of measures to ensure that all rock piles and stockpiles of ore, concentrate, overburden and other materials are maintained in a safe and stable condition. vi. Details of measures to ensure that all tailings, water and other impoundment structures are maintained in a safe and stable condition in accordance with the Code. vii. A schedule of protective measures to be implemented in order for the project to be considered in temporary suspension. 8. Rehabilitation measures — inactivity: i. Details of measures to restrict access to the project site, buildings and other structures to authorized persons. ii. Details of how all shafts, raises or open stopes are to be secured. iii. Details of how all portals of adits and declines are to be secured. iv. Details of measures to ensure that all other mine openings to surface that create a mine hazard are stabilized and secured. v. Details of measures to ensure that all mechanical and hydraulic systems are maintained in a no-load condition and that non-essential electrical systems are de-energized and all other electrical systems are made safe and secure. vi. Details of measures to monitor, maintain or rehabilitate all tailings impoundment areas. vii. Details of measures to monitor, maintain or rehabilitate all landfill or other waste management sites. viii. Details of measures to remove, dispose of, isolate or manage on site all petroleum products, chemicals and waste, including polychlorinated biphenyls (PCBs), and to ensure that all explosives are disposed of or removed from the site. ix. Details of measures to ensure that all rock piles and stockpiles of ore, concentrate, overburden and other materials are monitored and maintained in a physically and chemically safe and stable condition. x. Details of measures to ensure that all tailings, water and other impoundment structures are maintained in a safe and stable condition in accordance with the Code. xi. Details of a site inspection program to be conducted at least once every six months to ensure that the required rehabilitation measures are in place and how the site inspections will be recorded and reported to the Minister. xii. A schedule of the protective measures and other rehabilitation measures to be implemented in order for the project to be considered in a state of inactivity. 9. Rehabilitation measures — closed out: i. Details of how all shafts, raises or open stopes shall be secured in accordance with the Code. ii. Details of how all portals of adits and declines are to be secured in accordance with the Code. iii. Details of the measures to be implemented to ensure that all other mine openings to surface that create a mine hazard are stabilized and secured in accordance with the Code. iv. Details of the measures to be implemented to assess the stability of surface and subsurface mine workings and any measures to be used to ensure stability of the ground surface in accordance with the Code, including reports of all geotechnical studies required under the Code as of the date of the closure plan. v. Details of how all buildings, power transmission lines, waterlines, railways, pipelines, airstrips and other structures and infrastructure will be treated in accordance with the Code. vi. Details of how all machinery, equipment and storage tanks will be treated in accordance with the Code. vii. Details of how all transportation corridors will be treated in accordance with the Code. viii. Details of how all concrete structures, foundations and slabs shall be treated in accordance with the Code. ix. Details of how all petroleum products, chemicals and waste will be disposed of on site or removed and how all explosives will be disposed of or removed. x. Details of how any PCBs or PCB-contaminated material will be removed or managed on site. xi. Details of measures to close all landfill sites and other waste management sites. xii. Details of measures to sample and test soils in the vicinity of any petroleum product, chemical, explosive or waste storage or transfer sites, and details of the risk assessment and action plan for contaminated soil if contamination is found. xiii. Details of measures to ensure physical and chemical stability, erosion control and surface and ground water quality at all tailings areas. xiv. Details of measures to ensure physical and chemical stability, erosion control and surface and ground water quality at all rock piles and stockpiles of ore, concentrate, overburden and other materials. xv. Details of measures to breach or stabilize all tailings, water and other impoundment structures against static or dynamic loadings to ensure the containment of materials and the maintenance of the post-closure state. xvi. Details of measures to remove or make inoperable all decant structures, other than dam spillways. xvii. Details of measures to ensure that the physical structure of all water courses and drainage channels remaining on the site will be left so as to not require maintenance. xviii. Details of measures for the revegetation of the site in accordance with the Code. xix. A schedule of the protective measures and other rehabilitation measures to be implemented before the project can be considered closed out. 10. Monitoring: i. Details of the monitoring programs and procedures in accordance with the Code to ensure that the physical stability of mine hazards located on the site provide the level of protection required for each stage of closure, including the locations, methods and frequencies of monitoring and how the results of the monitoring will be recorded and reported to the Minister. ii. Details of the monitoring programs and procedures in accordance with the Code to ensure that the chemical stability of tailings, rock piles and stockpiles of ore, concentrate, overburden and other materials, and surface and subsurface effluents provide the level of protection required for each stage of closure, including the locations, methods and frequency of sampling, the parameters to be analyzed, the analytical methods to be used and how the results of the monitoring will be recorded and reported to the Minister. iii. Details of any biological monitoring programs and procedures to assess the effects of the project on any biological communities. These details shall include the locations, nature, methods and frequency of monitoring, the biological communities to be monitored and how the results of the monitoring will be recorded and reported to the Minister. 11. Expected site conditions: i. Details of the post-closure state. ii. Details of the site topography after close out if significant changes to the existing site topography are expected, including a topographic plan of legible scale and contour interval. iii. Details of the expected conditions, after close out, of all surface waters on or flowing through the site and any surface waters receiving flow from the site, including the expected quantity and physical and chemical quality as well as all expected final water elevations of all surface waters that may be affected by the project. iv. Details of the expected conditions, after close out, of all ground waters located within the site that may have been affected by the project, including the expected location of aquifers, the expected quantity, the expected physical and chemical quality, all expected final water elevations and the compatibility with expected land use of all ground waters that may be affected by the project. v. Details of the expected condition of the terrestrial plant and animal life communities, as compared to the condition of such communities before the start of the project, that may have been affected by the project, including the methods to be used to assess the health or quality of the communities to demonstrate that the project will sustain terrestrial plant and animal life and that the project can be considered closed out. vi. Details of the expected condition of the aquatic plant and animal life communities, as compared to the condition of such communities before the start of the project, that may have been affected by the project, including the methods to be used to assess the health or quality of the communities to demonstrate that the project will sustain aquatic plant and animal life and that the project can be considered closed out. 12. Costs: details of the expected costs of implementing the rehabilitation measures and monitoring programs required to close out the site, including at least a detailed expenditure schedule and an itemized estimate of capital costs and operating costs based on the market value of the material goods and services provided. 13. Financial assurance: i. The form and amount of the financial assurance provided. ii. All financial and commercial information used to establish the financial assurance. If the proponent intends to comply with a corporate financial test, the information required by subsection 18 (2) or 19 (2) of this Regulation shall be included. iii. In the case of phased financial assurance, a phasing schedule, supported by detailed costing information, that contains, A. for each phase, 1. estimated date ranges for the start and end of the phase, 2. a list of each mine hazard that will be constructed or materially impacted during the phase and a projected timeframe for the start of such activity, consistent with the proposed schedule for the project, 3. details of the amount of the expected costs detailed under paragraph 12 that would be specific to the rehabilitation measures required in respect of the listed mine hazards during the phase, itemized for each mine hazard, and 4. a description of the amount of financial assurance to be provided before the commencement of the phase, and B. in the case of a mine production closure plan only, 1. a list of all pre-existing mine hazards predating the start of the project, and 2. details of the amount of the expected costs detailed under paragraph 12 that would be specific to the rehabilitation measures required in respect of the listed pre-existing mine hazards, itemized for each mine hazard. 14. For each intended certified alternative measure, i. a description of the measure, and ii. details respecting the nature of the measure’s non-conformity with a standard, procedure or requirement of the Code. Form 1 proponent’s certificate (requirements are met) I (We) hereby certify that, (a) the attached closure plan complies in all respects with the Mining Act and its regulations, including the Mine Rehabilitation Code of Ontario; (b) the proponent relied on qualified persons in the preparation of the closure plan, where required under the Mining Act and its regulations, including the Mine Rehabilitation Code of Ontario; (c) the cost estimates of the rehabilitation work described in the attached closure plan are based on the market value cost of the goods and services required by the work; (d) the amount of financial assurance provided for in the attached closure plan is adequate and sufficient to cover the cost of the rehabilitation work required in order to comply with the Mining Act and its regulations, including the Mine Rehabilitation Code of Ontario; (e) (only if a form of phased financial assurance is provided for) the schedule set out for the phased financial assurance provided for in the attached closure plan meets the requirements of section 21 of Ontario Regulation 35/24 (Rehabilitation of Lands) made under the Mining Act; (f) the proponent has complied with any written direction regarding Aboriginal consultation provided by the Minister under subsection 9 (3) of Ontario Regulation 35/24 (Rehabilitation of Lands) made under the Mining Act; and (g) the attached closure plan constitutes full, true and plain disclosure of the rehabilitation work currently required to, (i) restore the site to its former use or condition to the extent required by Ontario Regulation 35/24 (Rehabilitation of Lands) made under the Mining Act, including the Mine Rehabilitation Code of Ontario, or, if applicable, (ii) change the use or condition of the site to a different use or condition determined by the Minister for the purposes of clause (b) of the definition of “rehabilitate” in subsection 139 (1) of the Mining Act. Form 2 proponent’s certificate (requirements are Not met) I (We) hereby certify that, (a) the attached closure plan complies in all respects with the Mining Act and its regulations, including the Mine Rehabilitation Code of Ontario, except to the extent described in the attached conditional filing order; (b) the conditional filing order permitting the submission of the closure plan is attached as an appendix, and the proponent has complied with all terms and conditions of the order that are required to be complied with as of the date of this certificate; (c) the proponent relied on qualified persons in the preparation of the closure plan, where required under the Mining Act and its regulations, including the Mine Rehabilitation Code of Ontario; (d) the cost estimates of the rehabilitation work described in the attached closure plan are based on the market value cost of the goods and services required by the work; (e) the amount of financial assurance provided for in the attached closure plan is adequate and sufficient to cover the cost of the rehabilitation work required in order to comply with the Mining Act and its regulations, including the Mine Rehabilitation Code of Ontario; (f) (only if a form of phased financial assurance is provided for) the schedule set out for the phased financial assurance provided for in the attached closure plan meets the requirements of section 21 Ontario Regulation 35/24 (Rehabilitation of Lands) made under the Mining Act; (g) the proponent has complied with any written direction regarding Aboriginal consultation provided by the Minister under subsection 9 (3) of Ontario Regulation 35/24 (Rehabilitation of Lands) made under the Mining Act; and (h) the attached closure plan constitutes full, true and plain disclosure of the rehabilitation work currently required to, (i) restore the site to its former use or condition to the extent required by Ontario Regulation 35/24 (Rehabilitation of Lands) made under the Mining Act, including the Mine Rehabilitation Code of Ontario, or (ii) change to a different use or condition determined by the Minister for the purposes of clause (b) of the definition of “rehabilitate” in subsection 139 (1) of the Mining Act. Form 3 Qualified Person certificate (Conforming Measures) I, (insert full legal name of qualified person), hereby certify that, (a) this certificate pertains to Part(s) (specify the Part or Parts) of the Mine Rehabilitation Code of Ontario; (b) I (choose one of the following statements), (i) am providing this certificate in my capacity as a professional engineer under the Professional Engineers Act, (ii) am a member of the Association of Professional Geoscientists of Ontario and am providing this certificate in my capacity as a professional geoscientist, (iii) am a member of The Ontario Association of Landscape Architects and am providing this certificate in my capacity as a landscape architect, (iv) am a member of the Ontario Institute of Professional Agrologists and am providing this certificate in my capacity as a professional agrologist, (v) am not a professional engineer under the Professional Engineers Act or a member of the Association of Professional Geoscientists of Ontario, The Ontario Association of Landscape Architects or the Ontario Institute of Professional Agrologists, but hold a university degree in science or engineering and have, in respect of this certificate’s subject matter, at least five years of relevant experience; (c) I am familiar with the provisions of Ontario Regulation 35/24 (Rehabilitation of Lands) made under the Mining Act, including of the Mine Rehabilitation Code of Ontario, that are relevant to the subject matter of this certificate; (d) I have examined the closure plan and made such other investigations as I believe to be necessary or desirable to provide this certificate; and (e) the rehabilitation measures set out in the closure plan conform to the standards, procedures and requirements of Part(s) (specify the Part or Parts) of the Mine Rehabilitation Code of Ontario. Form 4 Qualified Person certificate (Non-Conforming Measures) I, (insert full legal name of qualified person), hereby certify that, (a) this certificate pertains to Part(s) (specify the Part or Parts) of the Mine Rehabilitation Code of Ontario; (b) I (choose one of the following statements), (i) am providing this certificate in my capacity as a professional engineer under the Professional Engineers Act, (ii) am a member of the Association of Professional Geoscientists of Ontario and am providing this certificate in my capacity as a professional geoscientist, (iii) am a member of The Ontario Association of Landscape Architects and am providing this certificate in my capacity as a landscape architect, (iv) am a member of the Ontario Institute of Professional Agrologists and am providing this certificate in my capacity as a professional agrologist, (v) am not a professional engineer under the Professional Engineers Act or a member of the Association of Professional Geoscientists of Ontario, The Ontario Association of Landscape Architects or the Ontario Institute of Professional Agrologists, but hold a university degree in science or engineering and have, in respect of this certificate’s subject matter, at least five years of relevant experience; (c) I have examined the closure plan and made such other investigations as I believe to be necessary or desirable to provide this certificate; (d) I am familiar with the provisions of Ontario Regulation 35/24 (Rehabilitation of Lands) made under the Mining Act, including of the Mine Rehabilitation Code of Ontario, that are relevant to the subject matter of this certificate; (e) the rehabilitation measures set out in the closure plan conform to the standards, procedures and requirements of Part(s) (specify the Part or Parts) of the Mine Rehabilitation Code of Ontario, except with respect to the following non-conforming rehabilitation measures: (list the measures); and (f) each of the non-conforming rehabilitation measures, (i) is only non-conforming to the extent permitted in the conditional filing order being submitted with the closure plan, or (ii) meets or exceeds the objective specified in the applicable Part(s), and is consistent with one or more of, (A) recognized industry standards or best practices, (B) sound scientific principles, and (C) good engineering practice.
Read the REHABILITATION OF LANDS on e-Laws ↗

Made under Mining Act, R.S.O. 1990, c. M.14.