ON-SITE AND EXCESS SOIL MANAGEMENT, O. Reg. 406/19
Schedule 2
Cite as ON-SITE AND EXCESS SOIL MANAGEMENT, O. Reg. 406/19, Schedule 2 · current to November 11, 2026 · consolidated from January 1, 2026 · read from e-Laws on November 16, 2026
The text
Schedule 2 Non-Application of section 8 of the Regulation
1. Revoked: O. Reg. 555/22, s. 7.
2. Both of the following circumstances apply:
1. The amount of soil to be removed from the project area is 100 m3 or less.
2. The excess soil is directly transported to a waste disposal site that is not a Class 2 soil management site.
3. The reason for excavating the soil that will become excess soil is one of the following:
1. To alleviate an immediate danger to human life, the health of any persons, the natural environment, or to property.
2. The duty imposed by subsection 93 (1) of the Act.
3. An order made by any authority with jurisdiction to make the order.
4. Maintaining infrastructure in a fit state of repair, except if the excavation of soil is from a stormwater management pond for the purpose of maintaining the facility in a fit state of repair.
4. All of the following circumstances apply:
1. The project area is subject to section 8 by reason only of paragraph 2 of subsection 8 (1.1).
2. The excavated soil is only topsoil.
3. The topsoil is transported directly to a reuse site from the project area for use as topsoil at the reuse site.
5. All of the following circumstances apply:
1. The soil is excavated from an area within an enhanced investigation project area.
2. The amount of excavated soil is 100 m3 or less.
3. The project is a landscaping project, involving only landscape care and maintenance services, installing or replacing lamp posts, light poles, trees, shrubs, plants, lawns or gardens, and the construction of walkways, retaining walls, decks, fences and ponds.
4. Based on a report prepared by or under the supervision of a qualified person, including an assessment of past uses under section 11, it has been demonstrated that the part of the enhanced investigation project area from which the soil will be excavated is not likely to have been affected by the discharge of a contaminant.
6. Both of the following circumstances apply:
1. The excess soil is excavated as part of an infrastructure project.
2. The project leader for the infrastructure project intends, after removing the excess soil from the project area, to deposit it for final placement at a reuse site that is owned by the project leader or a public body and that is part of an infrastructure undertaking.
7. Both of the following circumstances apply:
1. The soil is being deposited at a local waste transfer facility.
2. The amount of soil to be deposited at the local waste transfer facility is 100 m3 or less.
Read the ON-SITE AND EXCESS SOIL MANAGEMENT on e-Laws ↗
Made under Environmental Protection Act, R.S.O. 1990, c. E.19.