ON-SITE AND EXCESS SOIL MANAGEMENT, O. Reg. 406/19
Section 12
Sampling and analysis plan, soil characterization report
Cite as ON-SITE AND EXCESS SOIL MANAGEMENT, O. Reg. 406/19, s. 12 · current to November 11, 2026 · consolidated from January 1, 2026 · read from e-Laws on November 16, 2026
The text
(1) Subject to subsection (3), if the project leader for a project is required to file a notice under section 8 in respect of the project and any of the circumstances set out in subsection (2) apply, the project leader shall ensure that, before filing the notice, a qualified person prepares or supervises the preparation of a sampling and analysis plan in accordance with the Soil Rules. O. Reg. 406/19, s. 12 (1); O. Reg. 555/22, s. 4.
(2) For the purposes of subsection (1), a sampling and analysis plan is required if any of the following circumstances apply:
1. The assessment of past uses prepared in accordance with section 11 or phase one environmental site assessment mentioned in paragraph 2 of subsection 11 (2) identifies a potentially contaminating activity within the meaning of Ontario Regulation 153/04.
2. Any part of the project area is or has ever been an enhanced investigation project area.
3. The project involves the excavation and removal of excess soil from a stormwater management pond. O. Reg. 406/19, s. 12 (2).
(3) A sampling and analysis plan is not required if the soil to be excavated is to be deposited at a Class 1 soil management site. O. Reg. 406/19, s. 12 (3).
(4) If a sampling and analysis plan is required to be prepared in respect of a project, the project leader shall,
(a) ensure that a qualified person implements or supervises the implementation of the plan;
(b) develop and apply written procedures to ensure that, as soil is excavated and stored in stockpiles, the soil is segregated and stockpiled in accordance with the Soil Rules and that any soil that is sampled and analysed is kept segregated from other soil; and
(c) before filing the notice on the Registry under section 8, ensure that a qualified person prepares or supervises the preparation of a soil characterization report in accordance with the Soil Rules. O. Reg. 406/19, s. 12 (4); O. Reg. 235/25, s. 12.
(5) A soil characterization report mentioned in clause (4) (c) shall include the following information:
1. The results of sampling and analysis and an assessment of those results, including a description of the parts of the project area that were sampled and analysed.
2. A description of which soil may be reused within the project area, with or without processing at the project area, and which soil may be deposited at a Class 1 soil management site, landfilling site or dump.
3. Having regard to the Excess Soil Standards, identification of the type of potential reuse sites to which excess soil from the project area may be transported for final placement. O. Reg. 406/19, s. 12 (5).
(6) If, before January 1, 2023, a project leader undertakes a sampling and analysis plan to analyze the concentration of contaminants of any soil in the project area that may become excess soil in respect of a project, the plan shall be deemed to satisfy the requirement for a sampling and analysis plan required by this section and a report that is prepared describing the results of implementing the sampling and analysis plan shall be deemed to satisfy the requirements of a soil characterization report set out in subsection (5) for that project. O. Reg. 775/20, s. 11; O. Reg. 388/22, s. 3.
Read the ON-SITE AND EXCESS SOIL MANAGEMENT on e-Laws ↗
Made under Environmental Protection Act, R.S.O. 1990, c. E.19.