(1) A community planning permit by-law comes into force on,
(a) the day after the last day for filing a notice of appeal, if there are no appeals; or
(b) the day after the day on which all the appeals are disposed of by the Tribunal, or such later date as the Tribunal may otherwise order, subject to subsection (2). O. Reg. 173/16, s. 9 (1); O. Reg. 75/18, s. 2 (1).
(2) If there are appeals that have not yet been disposed of, the Tribunal may, on its own initiative or on the motion of any person or public body, make an order providing that any part of the community planning permit by-law that is not in issue in such an appeal is deemed to have come into force on,
(a) the day after the last day for filing a notice of appeal; or
(b) such later date as the Tribunal may otherwise order. O. Reg. 173/16, s. 9 (2); O. Reg. 75/18, s. 2 (2).
(3) On the day the community planning permit by-law comes into force, all by-laws passed under section 34 of the Act are deemed to be repealed with respect to the area covered by the community planning permit by-law. O. Reg. 173/16, s. 9 (3).
(4) If subsection (2) applies, the relevant parts of by-laws passed under section 34 of the Act are deemed to be repealed with respect to the area covered by the part of the community planning permit by-law that is deemed to have come into force early. O. Reg. 173/16, s. 9 (4).
Read the COMMUNITY PLANNING PERMITS on e-Laws ↗
Made under Planning Act, R.S.O. 1990, c. P.13.