(1) A plan shall show,
(a) every right of way and easement affecting the land shown on the plan that is,
(i) described in a registered instrument, or
(ii) shown on a registered or deposited plan;
(b) the bearing and length of each straight line forming any surveyed limit or part of any surveyed limit, except that, in the case of a tier of subdivision units that is shown by the dimensions to be a series of parallelograms, the direction of each of the side lines of the subdivision units may be indicated by the bearings at both ends of the tier;
(c) the radius, arc length, chord length and chord bearing of each curved line forming any limit or part of any limit;
(d) the perpendicular or radial widths of all streets, lanes and public passages within the surveyed area of which the limits are parallel or concentric;
(e) the straight line distance and bearing between the points of intersection of street limits on the same side of the street and, if all or part of any intersection is on a curve, the radius, arc length, chord length and chord bearing of the curved portion;
(f) the location of the radial centre of an arc that forms a cul-de-sac, clearly defined with reference to the street or streets connected to the cul-de-sac;
(g) an accurately plotted simple north point;
(h) the scale, expressed in numerical form, to which the plan is drawn and a scale bar clearly identified as representing either feet or metres;
(i) if a survey has been integrated with a coordinate system in accordance with section 14,
(i) a table containing the coordinates of at least two monumented points related to the survey,
(ii) a note stating that the coordinates cannot, in themselves, be used to re-establish the corners or boundaries shown on the plan,
(iii) a note stating that the coordinates comply with subsection 14 (2),
(iv) a note stating the source from which the coordinates were derived and specifying the map projection, zone, datum and if applicable, adjustment epoch, and
(v) sufficient data to enable the location of the parcel of land surveyed to be ascertained in relation to the monumented points that are used to integrate the survey and that are shown in the table described in subclause (i);
(j) the location and form of all survey evidence found, conflicting or otherwise;
(k) the procedure used in re-establishing all existing boundaries forming part of a survey or on which a survey is dependent;
(l) the source of the distance or direction, if a distance or direction is set;
(m) sufficient data to permit the calculation of the error of closure in respect of the limits of each parcel of land shown on the plan; and
(n) if applicable, the name of the holder of the certificate of authorization. O. Reg. 216/10, s. 18 (1).
(2) If space does not permit the showing of bearings and lengths, as required by clauses (1) (b) and (c), in their normal position, they may be shown in schedule form on the plan. O. Reg. 216/10, s. 18 (2).