(1) The proponent shall prepare an environmental project report in accordance with subsection (2). O. Reg. 231/08, s. 9 (1). (2) The environmental project report shall contain the following: 1. A statement of the purpose of the transit or rail project and a summary of background information relating to the transit or rail project. 2. The final description of the transit or rail project, including a description of the preferred method of carrying out the transit or rail project, and a description of the other methods that were considered. 3. A map showing the site of the transit or rail project. 4. A description of the local environmental conditions at the site of the transit or rail project. 5. A description of all studies undertaken in relation to the transit or rail project, including, i. a summary of all data collected or reviewed, and ii. a summary of all results and conclusions. 6. The proponent’s assessment and evaluation of the impacts that the preferred method of carrying out the transit or rail project and other methods might have on the environment, and the proponent’s criteria for assessment and evaluation of those impacts. 7. A description of any measures proposed by the proponent for mitigating any negative impacts that the preferred method of carrying out the transit or rail project might have on the environment. 8. If mitigation measures are proposed under paragraph 7, a description of the means the proponent proposes to use to monitor or verify their effectiveness. 9. A description of any municipal, provincial, federal or other approvals or permits that may be required for the transit or rail project. 10. A consultation record, including, i. a description of the consultations carried out with interested persons, including Indigenous communities, ii. a list of the interested persons, including Indigenous communities, who participated in the consultations, iii. summaries of the comments submitted by interested persons, including Indigenous communities, iv. a summary of discussions that the proponent had with Indigenous communities under subsection 8 (5), and copies of all written comments submitted by Indigenous communities, and v. a description of what the proponent did to respond to concerns expressed by interested persons, including Indigenous communities. 11. A summary of each issue in respect of which notice was given to the Director of the Environmental Assessment Branch under subsection 10 (1), including, i. a description of the issue, ii. a description of what the proponent did to respond to the issue and the results of those efforts, and iii. the date that notices were given to the Director of the Environmental Assessment Branch under subsections 10 (1) and 10 (3). O. Reg. 231/08, s. 9 (2); O. Reg. 354/12, s. 5; O. Reg. 342/20, s. 1, 7; O. Reg. 52/24, s. 7, 16.
Read the TRANSIT AND RAIL PROJECT ASSESSMENT PROCESS on e-Laws ↗

Made under Environmental Assessment Act, R.S.O. 1990, c. E.18.