TRANSIT AND RAIL PROJECT ASSESSMENT PROCESS, O. Reg. 231/08
Section 10
Notice of issue, suspension of 120-day period
Cite as TRANSIT AND RAIL PROJECT ASSESSMENT PROCESS, O. Reg. 231/08, s. 10 · current to November 11, 2026 · consolidated from July 28, 2026 · read from e-Laws on November 16, 2026
The text
(1) If, at any time during the 120-day period referred to in subsection 6 (2), the proponent is of the opinion that the transit or rail project may have a negative impact on a matter of provincial importance that relates to the natural environment or has cultural heritage value or interest, or on the existing aboriginal or treaty rights of the aboriginal peoples of Canada, as recognized and affirmed in section 35 of the Constitution Act, 1982, the proponent may give written notice describing the issue to the Director of the Environmental Assessment Branch. O. Reg. 342/20, s. 8 (1); O. Reg. 52/24, s. 8 (1), 16.
(2) The proponent shall also post the notice on its website, if any. O. Reg. 231/08, s. 10 (2).
(3) If notice is given under subsection (1), the 120-day period referred to in subsection 6 (2) stops running until the proponent gives notices of resumption to the Director of the Environmental Assessment Branch. O. Reg. 231/08, s. 10 (3); O. Reg. 354/12, s. 6 (2); O. Reg. 342/20, s. 8 (2); O. Reg. 52/24, s. 8 (2).
Read the TRANSIT AND RAIL PROJECT ASSESSMENT PROCESS on e-Laws ↗
Made under Environmental Assessment Act, R.S.O. 1990, c. E.18.