The text
(1) It is a condition of an approval issued to a distributor for the use of a distribution system that the distributor, or any contractor or operator acting on the distributor’s behalf, report to the Authority any serious electrical incident of which they become aware within 48 hours after the occurrence and comply with this section. O. Reg. 22/04, s. 12 (1); O. Reg. 220/17, s. 3 (1).
(2) Where a serious electrical incident has occurred, a distributor, contractor or operator shall not interfere with or disturb, except in the interests of safety, saving life, relieving human suffering, continuity of service or preservation of property, any wreckage, article or thing at the scene of the incident that is connected to it and, in no case, shall wreckage, an article or a thing be carried away or destroyed unless an inspector so permits. O. Reg. 22/04, s. 12 (2).
(3) Where a serious electrical incident involving workers only is reported to the Ministry of Labour as required under the Occupational Health and Safety Act and that the Ministry has taken control of the scene of the incident, subsections (1) and (2) do not apply. O. Reg. 22/04, s. 12 (3).
(3.1) Upon request of the Authority, the distributor or any contractor or operator acting on the distributor’s behalf shall assist in an investigation under Part VIII of the Act into a serious electrical incident that involved the distributor’s assets. O. Reg. 220/17, s. 3 (2).
(4) In this section,
“critical injury” means an injury of a serious nature that,
(a) places life in jeopardy,
(b) produces unconsciousness,
(c) results in a substantial loss of blood,
(d) involves the fracture of a leg or arm but not a finger or toe,
(e) involves the amputation of a leg, arm, hand or foot but not a finger or toe,
(f) consists of burns to a major portion of the body, or
(g) causes the loss of sight in an eye;
“force majeure” includes acts of God, lightning strikes, weather, floods, natural catastrophes, civil commotions, sabotages, riots, invasion, insurrection, acts of terrorism, but does not include labour strikes, fires or explosions;
“meter” means any apparatus used for the purpose of making measurements of, or obtaining the basis of a charge for, electricity supplied to a purchaser;
“serious electrical incident” means,
(a) any electrical contact that caused death or critical injury to a person,
(b) any inadvertent contact with any part of a distribution system operating at 750 volts or above or with a meter, if the contact caused or had the potential to cause death or critical injury to a person, but not if the contact was caused by force majeure, or
(c) any fire or explosion in any part of a distribution system operating at 750 volts or above or in a meter, if the fire or explosion, as the case may be, caused or had the potential to cause death or critical injury to a person, but not if it was caused by force majeure;
“worker” means a worker as defined in section 1 of the Occupational Health and Safety Act. O. Reg. 22/04, s. 12 (4); O. Reg. 272/04, s. 3; O. Reg. 220/17, s. 3 (3-5).
Read the Electrical distribution safety on e-Laws ↗