Geophysical Exploration, N.B. Reg. 86-191

Schedule D

Procedures to Be Followed for Temporary and Permanent Abandonment of Shotholes and Testholes

Cite as Geophysical Exploration, N.B. Reg. 86-191, Schedule D · current to December 20, 2019 · read from New Brunswick Acts and Regulations on November 16, 2026

The text

1 A permittee shall ensure that a shothole is temporarily abandoned in accordance with the following procedure: (a) securely affix the explosive charge in the shothole to a winged sandpoint container; (b) place drill cuttings or other material approved by the Minister in the hole to secure the explosive charge at the depth at which it was loaded; (c) tightly pull the wire attached to the explosive charge to the ground surface; (d) place a plastic hole plug in the shothole at a depth of not less than 1 m below the ground surface; (e) place a bentonite sealing product on top of the plastic hole plug for a depth of at least 50 cm above the top of the plug followed by drilling cuttings or any soil or other material removed in the drilling of the shothole for a depth of at least 50 cm above the bentonite to fill the shothole to the surface and then thoroughly tamp the drill cuttings, soil or other material; and (f) spread all drill cuttings not required to fill the shothole evenly over the ground surrounding the hole. 2 A permittee shall ensure that a testhole is temporarily abandoned in accordance with the following procedure: (a) place a plastic hole plug in the testhole at a depth of not less than 1 m below the ground surface; (b) place a bentonite sealing product on top of the plastic hole plug for a depth of at least 50 cm above the top of the plug followed by drilling cuttings or any soil or other material removed in the drilling of the testhole for a depth of at least 50 cm above the bentonite to fill the testhole to the surface and then thoroughly tamp the drill cuttings, soil or other material; and (c) spread all drill cuttings not required to fill the testhole evenly over the ground surrounding the hole. 3 A permittee shall ensure that a shothole is permanently abandoned in accordance with the following procedure: (a) place a plastic hole plug in the shothole at a depth of not less than 1 m below the ground surface; (b) place a bentonite sealing product on top of the plastic hole plug for a depth of at least 50 cm above the top of the plug followed by drilling cuttings or any soil or other material removed in the drilling of the shothole for a depth of at least 50 cm above the bentonite to fill the shothole to the surface and then thoroughly tamp the drill cuttings, soil or other material; (c) spread all drill cuttings not required to fill the shothole evenly over the ground surrounding the hole; and (d) tightly pull the wire attached to the explosive charge and cut it level with the ground surface. 4 A permittee shall ensure that a testhole is permanently abandoned in accordance with the following procedure: (a) place a plastic hole plug in the testhole at a depth of not less than 1 m below the ground surface; (b) place a bentonite sealing product on top of the plastic hole plug for a depth of at least 50 cm above the top of the plug followed by drilling cuttings or any soil or other material removed in the drilling of the testhole for a depth of at least 50 cm above the bentonite to fill the testhole to the surface and then thoroughly tamp the drill cuttings, soil or other material; and (c) spread all drill cuttings not required to fill the testhole evenly over the ground surrounding the hole.
Read the Geophysical Exploration on the Province's website ↗

Made under Oil and Natural Gas Act, c. O-2.1.