Construction Prompt Payment and Adjudication Act, 2023, c.15

Section 13

Payments by subcontractors to subcontractors

Cite as Construction Prompt Payment and Adjudication Act, 2023, c.15, s. 13 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026

The text

(1) Subject to subsection (7), a subcontractor who receives full payment under subsection 12(1) shall pay the amount payable to each subcontractor who supplied services or materials included in the proper invoice under a subcontract with that subcontractor no later than seven days after receiving the payment from the contractor. (2) Subject to subsection (7), a subcontractor who receives a portion of the amount payable under a proper invoice from a contractor shall pay from the amount received the amount payable to each subcontractor who supplied services or materials included in the proper invoice under a subcontract with that subcontractor no later than seven days after receiving the payment from the contractor. (3) For the purposes of subsection (2), if more than one subcontractor is entitled to payment under a proper invoice, the amount payable shall be determined as follows: (a) if the amount not paid by the contractor is specific to services or materials supplied by a particular subcontractor or subcontractors, the remaining subcontractors shall be paid and any amount paid by the contractor in connection to the services or materials supplied by the subcontractors that are implicated in the dispute shall be paid to them on a proportionate basis; or (b) in any other case, all the subcontractors shall be paid on a proportionate basis. (4) Subject to subsections (6) and (7), if a contractor does not pay the full amount payable to a subcontractor within the time specified in subsection 12(1), the subcontractor shall, no later than the time specified in subsection (5), pay the amount payable to each subcontractor who supplied services or materials included in the proper invoice under a subcontract with that subcontractor, to the extent that the subcontractor was not paid fully under subsection (2). (5) For the purposes of subsection (4), a subcontractor shall pay the amount payable no later than (a) seven days after the subcontractor receives payment from the contractor, or (b) if no payment is made by the contractor to the subcontractor, 42 days after the contractor gave the proper invoice to the owner. (6) Subsection (4) does not apply with respect to an amount payable to a subcontractor if, no later than the time specified in subsection (8), the subcontractor required to pay under subsection (4) gives to the other subcontractor (a) a notice of non-payment in the form prescribed by regulation that includes (i) a statement that all or a portion of the amount payable to the subcontractor is not being paid within the time specified in subsection (4) due to non-payment by the contractor, (ii) the amount not being paid, and (iii) unless the non-payment by the contractor is a result of non-payment by the owner, an undertaking to refer the matter between the subcontractor and the contractor to adjudication in accordance with Part 3 no later than 21 days after giving the notice of non-payment to the subcontractor, and (b) a copy of any notice of non-payment received by the subcontractor in relation to the proper invoice. (7) A subcontractor who disputes the entitlement of another subcontractor to payment of an amount under a subcontract may refuse to pay all or a portion of the amount within the time specified in subsection (1), (2) or (4), as the case may be, if, no later than the time specified in subsection (8), the subcontractor gives to the other subcontractor a notice of non-payment in the form prescribed by regulation that includes the amount that the subcontractor refuses to pay and the reasons for the non-payment. (8) For the purposes of subsections (6) and (7), a subcontractor shall give a notice of non-payment no later than (a) seven days after receiving a notice of non-payment from a contractor under subsection 12(5) or (6), or (b) if no notice of non-payment was given by the contractor, 42 days after a proper invoice was given to the owner. (9) Subsections (1) and (2) apply with the necessary modifications to an amount payable to a subcontractor that is the subject of a notice under subsection (6), once the amount is paid by the contractor. (10) If a subcontractor who is required to make payments in accordance with this section requests confirmation of the date a contractor gave a proper invoice to an owner, the contractor shall provide that confirmation to the subcontractor as soon as the circumstances permit. (11) This section applies with the necessary modifications to a subcontractor who is entitled to payment in accordance with this section and to any amounts payable by that subcontractor to another subcontractor who supplied services or materials included in the proper invoice.
Read the Construction Prompt Payment and Adjudication Act on the Province's website ↗