Construction Prompt Payment and Adjudication Act, 2023, c.15
Section 12
Payments by contractors to subcontractors
Cite as Construction Prompt Payment and Adjudication Act, 2023, c.15, s. 12 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
(1) Subject to subsection (6), a contractor who receives full payment of the amount payable under a proper invoice from an owner within the time specified in section 10 shall pay the amount payable to each subcontractor who supplied services or materials included in the proper invoice under a subcontract with the contractor no later than seven days after receiving the payment from the owner.
(2) Subject to subsection (6), a contractor who receives a portion of the amount payable under a proper invoice from an owner within the time specified in section 10 shall pay from the amount received the amount payable to each subcontractor who supplied services or materials included in the proper invoice under a subcontract with the contractor no later than seven days after receiving the payment from the owner.
(3) For the purposes of subsection (2), if more than one subcontractor is entitled to payment, the amount payable shall be determined as follows:
(a) if the amount not paid by the owner is specific to services or materials supplied by a particular subcontractor or subcontractors, the remaining subcontractors shall be paid and any amount paid by the owner in connection to the services or materials supplied by the subcontractors that are implicated in the dispute shall be paid to them on a proportionate basis; or
(b) in any other case, all the subcontractors shall be paid on a proportionate basis.
(4) Subject to subsections (5) and (6), if an owner does not pay the full amount payable under a proper invoice within the time specified in section 10, the contractor shall pay the amount payable to each subcontractor who supplied services or materials included in the proper invoice under a subcontract with the contractor, to the extent that the subcontractor was not paid fully under subsection (2), no later than 35 days after giving the proper invoice to the owner.
(5) Subsection (4) does not apply with respect to an amount payable to a subcontractor if, no later than the time specified in subsection (7), the contractor gives to the subcontractor
(a) a notice of non-payment in the form prescribed by regulation that includes
(i) a statement that all or a portion of the amount payable to the subcontractor is not being paid within the time specified in subsection (4) due to non-payment by the owner,
(ii) the amount not being paid, and
(iii) an undertaking to refer the matter between the contractor and the owner to adjudication in accordance with Part 3 no later than 21 days after giving the notice of non-payment to the subcontractor, and
(b) a copy of any notice of non-payment given to the contractor by the owner under section 11.
(6) A contractor who disputes the entitlement of a subcontractor to payment of an amount under a subcontract may refuse to pay all or a portion of the amount within the time specified in subsection (1), (2) or (4), as the case may be, if, no later than the time specified in subsection (7), the contractor gives to the subcontractor a notice of non-payment in the form prescribed by regulation that includes the amount that the contractor refuses to pay and the reasons for the non-payment.
(7) For the purposes of subsections (5) and (6), a contractor shall give a notice of non-payment no later than
(a) seven days after receiving a notice of non-payment from an owner under section 11, or
(b) if no notice of non-payment was given by the owner, 35 days after giving a proper invoice to the owner.
(8) Subsections (1) and (2) apply with the necessary modifications to an amount payable to a subcontractor that is the subject of a notice under subsection (5), once the amount is paid by the owner.
Read the Construction Prompt Payment and Adjudication Act on the Province's website ↗