Construction Remedies Act, 2020, c.29
Section 34
Holdback
Cite as Construction Remedies Act, 2020, c.29, s. 34 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
(1) An owner who is liable to pay for the supply of services or materials under a contract under which a lien may arise shall retain a holdback equal to 10% of the contract price by retaining an amount equal to 10% of the value of the services or materials supplied under the contract, as they are actually supplied, until the expiry of the holdback period in subsection 47(1) or (2), as the case may be.
(2) If a contract has been certified or declared to be substantially performed under section 41 and there are services or materials remaining to be supplied to complete the contract, an owner who is liable to pay under the contract shall retain a holdback equal to 10% of the contract price of the services or materials remaining to be supplied by retaining an amount equal to 10% of the value of the services or materials remaining to be supplied, as they are actually supplied, until the expiry of the holdback period in subsection 47(3).
(3) The requirement to retain a holdback under subsection (1) or (2) applies whether or not a contract provides for instalment payments or for payment on completion and, in order to comply with that requirement, an owner shall deduct 10% from any payment made under the contract.
(4) In the case of a contract for which a contractor is required to provide a labour and material payment bond and performance bond to an owner under subsection 83(4), if the owner is the Crown, the percentage referred to in subsections (1), (2) and (3) shall be read as 5%.
(5) If a mortgagee is a financial institution and is authorized by an owner to disburse the money secured by a mortgage, the mortgagee may retain as a holdback the amount required to be retained by the owner under subsection (1) or (2) and the retention by the mortgagee of that amount is deemed to be compliance with this section by the owner.
(6) A mortgagee that retains or agrees to retain a holdback under subsection (5)
(a) has the same rights and obligations in relation to the holdback as if it had been retained by the owner, and
(b) is liable to the owner or any lienholder who suffers loss or damage as a result of the failure of the mortgagee
(i) to retain the holdback as agreed, or
(ii) to fulfil the mortgagee’s obligations in relation to the holdback.
(7) Every lienholder of a lien that arises under a contract has a charge on the holdback required under this section to be retained by the owner with respect to the contract.