Construction Remedies Act, 2020, c.29

Section 33

Removal of materials

Cite as Construction Remedies Act, 2020, c.29, s. 33 · current to June 16, 2023 · read from New Brunswick Acts and Regulations on November 16, 2026

The text

(1) During the existence of a lien, no part of any materials that are affected by the lien may be removed to the prejudice of the lien. (2) Materials actually supplied for the purpose set out in subsection 20(1) are subject to a lien in favour of the person supplying them until they are incorporated into the improvement. (3) While a lien in subsection (2) exists, the materials are not subject to execution or other process to enforce any debt other than that for the purchase money of those materials.