Early public notification
Cite as Pipeline Filing, N.B. Reg. 2006-3, s. 4 · current to December 18, 2020 · read from New Brunswick Acts and Regulations on November 16, 2026
The text
(1) Unless the Board otherwise directs, an application for a permit under Part 2 of the Act shall be accompanied by the information required by subsection (4).
(2) With respect to early public notification, the application shall include evidence to show that there has been meaningful public input at a local and regional level during the planning and design phase of the project to ensure that those, including aboriginal communities, who may be affected by the project
(a) are made aware of the project as early as possible, and
(b) are given an opportunity to express their views to the applicant in advance of the application
in order that the concerns of the public and aboriginal communities are addressed in the application.
(3) Prior to filing an application under subsection (1), an applicant shall, after first obtaining ex parte Board approval of the proposed elements of the public information program described in paragraphs (a) to (f), do the following:
(a) implement a public information program to explain the project applied for and its potential effects and to allow an opportunity for public comment, providing as a minimum a map to identify the project location and sufficient information for the potential effects of the project to be identified;
(b) provide interested persons, including aboriginal communities, adequate time to comment on the project;
(c) respond to any relevant questions that may be raised by such interested persons;
(d) provide such interested persons with information regarding Board procedures for examining the application, and the Board’s address for obtaining information and expressing concerns directly to the Board;
(e) if changes occur as a result of the comments received, notify those who made the comments and initiate a public notification program for persons affected by the project as a result of the changes; and
(f) if changes to the project are made other than for the reasons in paragraph (c), initiate a public notification program for persons who would be affected.
(4) The application filed with the Board shall include a description of the public information program conducted under subsection (3), including, but not limited to,
(a) a description of the means and date of public notification and the date and location of meetings, if any;
(b) a summary of public comments received and concerns expressed about the project’s potentially adverse effects; and
(c) with respect to the comments and concerns described in paragraph (b), a summary of the response to the interested person, including
(i) a summary of the measures the applicant has taken or intends to take to resolve those concerns, or
(ii) an explanation of why the applicant considers no further action is required with respect to those concerns.
(5) An applicant may request exemption from the requirements of subsections (3) and (4)
(a) by demonstrating that an equivalent notification process has been carried out which identified the project which is being applied for,
(b) by demonstrating that the potential effects of the project are insignificant, or
(c) by demonstrating that the application pertains to installations which relates to
(i) work contained within the confines of land owned or leased by the applicant, except where those installations or activities
(A) relate to an increase in the storage or disposal of toxic substances,
(B) could result in increased noise emissions,
(C) could result in increased emissions of air contaminants, or
(D) will result in local nuisance potential, including the potential for increased noise or traffic,
(ii) additional acquisitions required to support the day-to-day operations of a pipeline (for example, standby plant or materials and supplies), or
(iii) work performed which relates to required contingency projects such as emergency repairs.
(6) For greater certainty, the definition of land as used in subparagraph (5)(c)(i) does not include land upon which the applicant holds an easement only.
Read the Pipeline Filing on the Province's website ↗