Builders Lien Act, SBC 1997, c. 45
Section 9
Rights on payment of holdback
Cite as Builders Lien Act, SBC 1997, c. 45, s. 9 · read from BC Laws on November 17, 2026
The text
(1) A contractor is entitled to receive, from the holdback retained by the owner from the contractor, an amount equal to the holdback amount applicable to a subcontract if
(a) a certificate of completion has been issued in respect of the subcontract to which the contractor was a party, and
(b) the holdback period established under section 8 (1) has expired without any claims of lien being filed that arose under the subcontract.
(2) An owner is deemed to have complied with the requirements of section 4 even if the amount retained has been reduced to a lesser percentage than is required by that section if
(a) an amount is paid to a contractor in accordance with subsection (1) of this section, and
(b) the amount retained by the owner would have complied with the requirements of section 4 had no payments been made under this section.
(3) Subsections (1) and (2) apply if a certificate of completion is given in relation to a subcontract to which a contractor is not a party.
(4) If a contractor is entitled to an amount under subsection (1), payment may be made from the holdback account established under section 5.
Read the Builders Lien Act on BC Laws ↗