Builders Lien Act, SBC 1997, c. 45
Section 8
Holdback period
Cite as Builders Lien Act, SBC 1997, c. 45, s. 8 · read from BC Laws on November 17, 2026
The text
(1) If a certificate of completion is issued with respect to a contract or subcontract, the holdback period in relation to
(a) the contract or subcontract, and
(b) any subcontract under the contract or subcontract
expires at the end of 55 days after the certificate of completion is issued.
(2) The holdback period for a contract or subcontract that is not governed by subsection (1) expires at the end of 55 days after
(a) the head contract is completed, abandoned or terminated, if the owner engaged a head contractor, or
(b) the improvement is completed or abandoned, if paragraph (a) does not apply.
(3) [Not in force.]
(4) Payment of a holdback required to be retained under section 4 may be made after expiry of the holdback period, and all liens of the person to whom the holdback is paid, and of any person engaged by or under the person to whom the holdback is paid, are then discharged unless in the meantime a claim of lien is filed by one of those persons or proceedings are commenced to enforce a lien against the holdback.