Builders Lien Act, SBC 1997, c. 45

Section 21

When claim of lien takes effect

Cite as Builders Lien Act, SBC 1997, c. 45, s. 21 · read from BC Laws on November 17, 2026

The text

A claim of lien filed under this Act takes effect from the time work began or the time the first material was supplied for which the lien is claimed, and it has priority over all judgments, executions, attachments and receiving orders recovered, issued or made after that date.
Read the Builders Lien Act on BC Laws ↗