Builders Lien Act, SBC 1997, c. 45

Section 20

Time for filing claim of lien

Cite as Builders Lien Act, SBC 1997, c. 45, s. 20 · read from BC Laws on November 17, 2026

The text

(1) If a certificate of completion has been issued with respect to a contract or subcontract, the claims of lien of (a) the contractor or subcontractor, and (b) any persons engaged by or under the contractor or subcontractor may be filed no later than 45 days after the date on which the certificate of completion was issued. (2) A claim of lien that is not governed by subsection (1) may be filed no later than 45 days after (a) the head contract has been completed, abandoned or terminated, if the owner engaged a head contractor, or (b) the improvement has been completed or abandoned, if paragraph (a) does not apply. (3) Subsection (1) does not operate to extend or renew the time for filing of a claim of lien if (a) that time would otherwise be determined with reference to the time an earlier certificate of completion was issued, or (b) time had started to run under subsection (2). (4) On the filing of a claim of lien under this Act, the registrar or gold commissioner has no duty to inquire as to whether or not the lien claimant has complied with the time limit for filing the claim of lien.
Read the Builders Lien Act on BC Laws ↗