Utilities Commission Act, RSBC 1996, c. 473
Section 46
Procedure on application
Cite as Utilities Commission Act, RSBC 1996, c. 473, s. 46 · read from BC Laws on November 17, 2026
The text
(1) An applicant for a certificate of public convenience and necessity must file with the commission information, material, evidence and documents that the commission prescribes.
(2) The commission has a discretion whether or not to hold any hearing on the application.
(3) Subject to subsections (3.1) to (3.3), the commission may, by order, issue or refuse to issue the certificate, or may issue a certificate of public convenience and necessity for the construction or operation of a part only of the proposed facility, line, plant, system or extension, or for the partial exercise only of a right or privilege, and may attach to the exercise of the right or privilege granted by the certificate, terms, including conditions about the duration of the right or privilege under this Act as, in its judgment, the public convenience or necessity may require.
(3.1) In deciding whether to issue a certificate under subsection (3) applied for by a public utility other than the authority, the commission must consider
(a) the applicable of British Columbia's energy objectives,
(b) the most recent long-term resource plan filed by the public utility under section 44.1, if any, and
(c) the extent to which the application for the certificate is consistent with the applicable requirements under sections 6 and 19 of the Clean Energy Act.
(3.2) Section (3.1) does not apply if the commission considers that the matters addressed in the application for the certificate were determined to be in the public interest in the course of considering a long-term resource plan under section 44.1.
(3.3) In deciding whether to issue a certificate under subsection (3) to the authority, the commission, in addition to considering the interests of persons in British Columbia who receive or may receive service from the authority, must consider
(a) British Columbia's energy objectives,
(b) the most recent of the following documents:
(i) an integrated resource plan approved under section 4 of the Clean Energy Act before the repeal of that section;
(ii) a long-term resource plan filed by the authority under section 44.1 of this Act, and
(c) the extent to which the application for the certificate is consistent with the requirements under section 19 of the Clean Energy Act.
(4) If a public utility desires to exercise a right or privilege under a consent, franchise, licence, permit, vote or other authority that it proposes to obtain but that has not, at the date of the application, been granted to it, the public utility may apply to the commission for an order preliminary to the issue of the certificate.
(5) On application under subsection (4), the commission may make an order declaring that it will, on application, under rules it specifies, issue the desired certificate, on the terms it designates in the order, after the public utility has obtained the proposed consent, franchise, licence, permit, vote or other authority.
(6) On evidence satisfactory to the commission that the consent, franchise, licence, permit, vote or other authority has been secured, the commission must issue a certificate under section 45.
(7) The commission may, by order, amend a certificate previously issued, or issue a new certificate, for the purpose of renewing, extending or consolidating a certificate previously issued.
(8) A public utility to which a certificate is, or has been, issued, or to which an exemption is, or has been, granted under section 45 (4), is authorized, subject to this Act, to construct, maintain and operate the plant, system or extension authorized in the certificate or exemption.
Read the Utilities Commission Act on BC Laws ↗