Utilities Commission Act, RSBC 1996, c. 473
Section 45
Certificate of public convenience and necessity
Cite as Utilities Commission Act, RSBC 1996, c. 473, s. 45 · read from BC Laws on November 17, 2026
The text
(1) Except as otherwise provided, after September 11, 1980, a person must not begin the construction or operation of a public utility plant or system, or an extension of either, without first obtaining from the commission a certificate that public convenience and necessity require or will require the construction or operation.
(2) For the purposes of subsection (1), a public utility that is operating a public utility plant or system on September 11, 1980 is deemed to have received a certificate of public convenience and necessity, authorizing it
(a) to operate the plant or system, and
(b) subject to subsection (5), to construct and operate extensions to the plant or system.
(3) Nothing in subsection (2) authorizes the construction or operation of an extension that is a reviewable project under the Environmental Assessment Act.
(4) The commission may, by regulation, exclude a utility plant or categories of utility plants from the operation of subsection (1).
(5) If it appears to the commission that a public utility should, before constructing or operating an extension to a utility plant or system, apply for a separate certificate of public convenience and necessity, the commission may, not later than 30 days after construction of the extension is begun, order that subsection (2) does not apply in respect of the construction or operation of the extension.
(6) A public utility must file with the commission at least once each year a statement in a form prescribed by the commission of the extensions to its facilities that it plans to construct.
(6.1) and (6.2) [Repealed 2008-13-8.]
(7) Except as otherwise provided, a privilege, concession or franchise granted to a public utility by a municipality or other public authority after September 11, 1980 is not valid unless approved by the commission.
(8) The commission must not give its approval unless it determines that the privilege, concession or franchise proposed is necessary for the public convenience and properly conserves the public interest.
(9) In giving its approval, the commission
(a) must grant a certificate of public convenience and necessity, and
(b) may impose conditions about
(i) the duration and termination of the privilege, concession or franchise, or
(ii) construction, equipment, maintenance, rates or service,
as the public convenience and interest reasonably require.