Data Centre Facility and Hydrogen Production Facility Power Supply Regulation, B.C. Reg. 8/2026

Section 1

Definitions

Cite as Data Centre Facility and Hydrogen Production Facility Power Supply Regulation, B.C. Reg. 8/2026, s. 1 · last amended January 30, 2026 · read from BC Laws on November 17, 2026

The text

In this regulation: “Act” means the Utilities Commission Act; “A.I. data centre” means a data centre, other than a cryptocurrency mining project, in which 10 percent or more of the electricity supplied to it is or will be used for (a) computational tasks related to artificial intelligence, (b) processing and storing data related to the computational tasks referred to in paragraph (a), or (c) powering equipment and other infrastructure used for the purposes referred to in paragraphs (a) and (b); “A.I. data centre purposes” means the use of electricity in or for an A.I. data centre; “applicable facility” means (a) an A.I. data centre, (b) a conventional data centre, or (c) a hydrogen-for-export facility; “competitive process” means a process established by the authority under section 4 (1) (a) or (b); “conventional data centre” means a data centre, other than an A.I. data centre, the primary purpose of which is storage or processing of electronic data; “conventional data centre purposes” means the use of electricity in or for a conventional data centre; “cryptocurrency mining project” means a project to mine cryptocurrency; “design deposit” means a payment made to the authority to cover all or a portion of the estimated costs of designing the upgrades to the authority's electric distribution system that would be necessary to connect an applicable facility to the authority's electricity distribution system; “distribution non-queue customer” means an existing customer of the authority (a) whose existing facility is connected to the authority's electricity distribution system at a voltage of 25 kV or less, and (b) who (i) requests or has requested incremental capacity for the facility, and (ii) did not pay a design deposit to the authority before the reference date; “existing facility” means any facility to which electricity service is supplied by the authority; “facilities study agreement” means an agreement (a) between the authority and a person who operates or proposes to operate a facility, (b) that is in the form of agreement commonly referred to by the authority as a "facilities study agreement", and (c) that provides for an evaluation by the authority of the work that would be necessary to connect the applicable facility to the authority's transmission system; “hydrogen-for-export facility” means a hydrogen production facility that produces hydrogen any of which is to be exported for use outside Canada; “hydrogen-for-export facility purposes” means the use of electricity in or for a hydrogen-for-export facility; “incremental capacity” means additional electricity capacity a person requests for a listed purpose; “listed purpose” has the meaning given to it in section 21.1 (1) of the Act; “minimum requirements” means the requirements described in section 4 (3) (b); “new high-voltage (non-queue) project” means a project respecting an applicable facility that satisfies the following criteria: (a) the project proponent requests at least 10 MW of capacity; (b) the project would be connected to the authority's electricity transmission system at a voltage of 60 kV or higher; (c) a system impact study agreement was not entered into in respect of the project prior to the reference date; “new low-voltage (no deposit) project” means a project respecting an applicable facility that satisfies the following criteria: (a) the project proponent requests at least 10 MW of capacity; (b) the project would be connected to the authority's electricity distribution system at a voltage of 25 kV or less; (c) a design deposit in respect of the project was not paid to the authority prior to the reference date; “proposed high-voltage (SISA) project” means a project respecting an applicable facility that satisfies the following criteria: (a) the project proponent has requested at least 10 MW of capacity; (b) the project would be connected to the authority's electricity transmission system at a voltage of 60 kV or higher; (c) a system impact study agreement respecting the project was entered into before the reference date; (d) a facilities study agreement respecting the project was not entered into before the reference date; “reference date” means February 1, 2026; “system impact study agreement” means an agreement (a) between the authority and a person who operates or proposes to operate a facility, (b) that is in the form of agreement commonly referred to by the authority as a "system impact study agreement", and (c) that provides for an evaluation by the authority of (i) the effects on the authority's transmission system of interconnecting the applicable facility to the authority's transmission system, and (ii) the modifications to the authority's transmission system that would be necessary to connect the applicable facility to the authority's transmission system, including modifications to maintain the reliability of the authority's transmission system; “transmission in-queue customer” means an existing customer of the authority (a) whose existing facility is connected to the authority's electricity transmission system at a voltage of 60 kV or higher, and (b) who (i) requested incremental capacity for the facility before the reference date, (ii) entered into a system impact study agreement before the reference date, and (iii) did not enter into a facilities study agreement before the reference date; “transmission non-queue customer” means an existing customer of the authority (a) whose existing facility is connected to the authority's electricity transmission system at a voltage of 60 kV or higher, and (b) who (i) requests or has requested incremental capacity for the facility, and (ii) did not enter into a system impact study agreement before the reference date; “wholesale electric utility” means a customer of the authority that purchases electricity from the authority for the primary purpose of reselling the electricity to its own customers.
Read the Data Centre Facility and Hydrogen Production Facility Power Supply Regulation on BC Laws ↗

Made under Utilities Commission Act, RSBC 1996, c. 473.