Energy Resource Road Regulation, B.C. Reg. 56/2013
Section 13.1
Maintenance and deactivation of borrow pits
Cite as Energy Resource Road Regulation, B.C. Reg. 56/2013, s. 13.1 · last amended September 1, 2023 · read from BC Laws on November 17, 2026
The text
(1) A road permit holder who holds an authorization for a borrow pit that the road permit holder has used for construction, maintenance or deactivation of the energy resource road must ensure that the cut slopes of the borrow pit are
(a) stable, and
(b) graded to a resting angle that
(i) facilitates reasonable egress by wildlife and livestock, and
(ii) does not exceed a grade of 2:1.
(2) A road permit holder who holds an authorization for a borrow pit described in subsection (1) that the road permit holder is not using for construction, maintenance or deactivation of the energy resource road must deactivate the borrow pit, as soon as weather and ground conditions permit, by
(a) spreading topsoil evenly around the perimeter and edges of the borrow pit, and
(b) revegetating the perimeter and edges of the borrow pit with ecologically suitable species.
Read the Energy Resource Road Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.