Processing Facility Regulation, B.C. Reg. 48/2021
Section 6
Development of management system
Cite as Processing Facility Regulation, B.C. Reg. 48/2021, s. 6 · last amended March 10, 2026 · read from BC Laws on November 17, 2026
The text
(1) Before construction of a processing facility begins, the processing facility permit holder must develop a management system to
(a) anticipate potential hazards, and
(b) manage potential hazards throughout the life cycle of the processing facility, in a systematic, comprehensive and proactive manner to prevent the hazards from occurring and to mitigate the effects of any hazards that do occur.
(2) A processing facility permit holder must ensure that the management system for the processing facility
(a) addresses all activities with respect to the design, construction, testing, operation, suspension of operations and decommissioning of the processing facility,
(b) includes
(i) Repealed. [B.C. Reg. 181/2022, App. 4, s. 1.]
(ii) an environmental management program that details the processes and procedures to minimize the adverse effect that the processing facility could have on the environment over the facility's life cycle,
(iii) an integrity management program that details the processes and procedures to maintain structures and equipment of the processing facility to avoid the failure of those structures and that equipment, and
(iv) a management of change program that details the processes and procedures to identify and manage any change that could adversely affect safety, security or environmental protection,
(c) takes into account the findings and recommendations of the reports referred to in section 4 (4) [required reports], and
(d) conforms to all requirements of the standard referred to in section 2 (2) (k) [process safety management].
Read the Processing Facility Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.