Processing Facility Regulation, B.C. Reg. 48/2021

Section 20

Notices of equipment and shutdowns

Cite as Processing Facility Regulation, B.C. Reg. 48/2021, s. 20 · last amended March 10, 2026 · read from BC Laws on November 17, 2026

The text

A processing facility permit holder must notify the regulator at least 24 hours before doing either of the following: (a) putting new or modified equipment into service; (b) beginning a planned shutdown of the processing facility or part of the processing facility.
Read the Processing Facility Regulation on BC Laws ↗

Made under Energy Resource Activities Act, SBC 2008, c. 36.