Processing Facility Regulation, B.C. Reg. 48/2021
Section 14
Pre-operation testing
Cite as Processing Facility Regulation, B.C. Reg. 48/2021, s. 14 · last amended March 10, 2026 · read from BC Laws on November 17, 2026
The text
(1) Before operation of any part of a processing facility begins, the processing facility permit holder must do all of the following:
(a) inspect and test
(i) components and systems in accordance with the engineering design and the requirements of the codes and standards,
(ii) control and safety critical devices and systems to verify that the devices and systems are operating in accordance with the engineering design, and
(iii) fire suppression systems, if any are included in the engineering design under section 7 (2) (d) [engineering design and siting];
(b) conduct leak tests of equipment and piping systems;
(c) conduct any other inspections or tests reasonably necessary to ensure that the processing facility is safe to operate.
(2) A processing facility permit holder must give to the regulator a schedule of when the inspections and tests referred to in subsection (1) will be conducted.
(3) If an official designated under section 7 (4) of the Act for the purposes of this section has reason to believe that an inspection or test should be witnessed, given risks to safety or the environment or of product loss,
(a) the official may give notice to the processing facility permit holder requiring that the inspection or test not be conducted unless witnessed by an official, and
(b) the processing facility permit holder must give notice to the official
(i) of the date that the inspection or test is to be conducted, at least 7 days but no more than 14 days before that date, and
(ii) of any change to that date, at least 2 days before that date.
(4) A processing facility permit holder must not begin to operate any part of a processing facility unless
(a) an inspection or test identified in a notice under subsection (3) (a) has been witnessed by an official, and
(b) the results of all inspections and tests conducted under this section indicate that it is safe to operate the processing facility.
Read the Processing Facility Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.