Processing Facility Regulation, B.C. Reg. 48/2021

Section 13

Site management after construction

Cite as Processing Facility Regulation, B.C. Reg. 48/2021, s. 13 · last amended March 10, 2026 · read from BC Laws on November 17, 2026

The text

(1) In this section, “disturbed land” means land within an operating area that (a) was disturbed during construction of a processing facility, and (b) is not required for the safe and efficient operation of the processing facility. (2) A processing facility permit holder must manage the surface of disturbed land by (a) removing all structures that are not required for the operation of the processing facility, and (b) restoring the surface of areas that will not be required for the operation of the processing facility to a state that eliminates hazards, enables weed and precipitation run-off control and prevents erosion. (3) Work under subsection (2) must be (a) carried out during construction of the processing facility, to the extent practicable given weather, ground and other conditions, and (b) completed as soon as practicable after operation of the processing facility begins, if the work could not practicably be completed during construction.
Read the Processing Facility Regulation on BC Laws ↗

Made under Energy Resource Activities Act, SBC 2008, c. 36.