Groundwater Protection Regulation, B.C. Reg. 39/2016
Section 73
Decommissioning temporary wells
Cite as Groundwater Protection Regulation, B.C. Reg. 39/2016, s. 73 · last amended December 1, 2022 · read from BC Laws on November 17, 2026
The text
The owner of a temporary well must ensure that, within 90 days after drilling is completed, the temporary well is
(a) decommissioned in accordance with section 71 [requirements for decommissioning wells] or 72, as applicable, or
(b) made into a permanent well that meets the standards and requirements of the Act and this regulation that apply to a permanent well of the applicable class.
Read the Groundwater Protection Regulation on BC Laws ↗
Made under Water Sustainability Act, SBC 2014, c. 15.