Groundwater Protection Regulation, B.C. Reg. 39/2016
Section 24
Multiple annular spaces
Cite as Groundwater Protection Regulation, B.C. Reg. 39/2016, s. 24 · last amended December 1, 2022 · read from BC Laws on November 17, 2026
The text
(1) If an annular space is created during the installation of a surface casing, the person responsible for drilling the well must
(a) subject to paragraph (b), remove the surface casing and install the surface seal between the next outermost casing and the geological formation, or
(b) if the surface casing cannot be removed,
(i) excavate the immediate area around the surface casing,
(ii) install sealant in the immediate area around the surface casing, as shown in Figure 2 of Schedule 5, to a length that is not less than 1 m and extends laterally from the surface casing to completely fill the excavated area, and
(iii) install sealant in the next outermost annular space, as shown in Figure 2 of Schedule 5, to a length that is not less than the minimum length required under section 22 (3) (c) [surface seal — general requirements].
(2) Subject to subsection (1) (b), the open annular space, if any, between multiple casings must be effectively capped with a well cap or sealed with a surface seal.
Read the Groundwater Protection Regulation on BC Laws ↗