Groundwater Protection Regulation, B.C. Reg. 39/2016
Section 19
Siting of recharge wells and injection wells
Cite as Groundwater Protection Regulation, B.C. Reg. 39/2016, s. 19 · last amended December 1, 2022 · read from BC Laws on November 17, 2026
The text
(1) Before a recharge well or injection well is constructed for the purpose of conveying urban runoff into the ground,
(a) the owner of the proposed recharge well or injection well must retain a professional who has competency in the field of hydrogeology or geotechnical engineering to design the proposed well, and
(b) the professional must
(i) design the proposed well so that the proposed well does not cause a significant adverse impact on the quality of water in an aquifer or in another well that diverts water from the aquifer, and
(ii) specify the following distances in the design:
(A) a minimum horizontal distance between the proposed well and an existing water supply well;
(B) a minimum vertical distance between the point of infiltration of the proposed well and the water table below to ensure that the point of infiltration of the proposed well is and will remain above the water table at all times.
(2) If the point of infiltration of treated water for a proposed recharge well or injection well is below the seasonal high water table, the professional, or the owner of the proposed recharge well or injection well, must submit the design described in subsection (1) to an engineer, who may
(a) accept the design, and may specify terms and conditions on the acceptance, and
(b) determine whether the recharge well or injection well may be exempted from the minimum vertical distance specification described in subsection (1) (b) (ii) (B).
(3) The person responsible for drilling a proposed recharge well or injection well must include the accepted design referred to in subsection (2), including the terms and conditions, if any, specified by the engineer with the well construction report if that report is required under section 76 [well construction reports submitted to both comptroller and well owner].
(4) The owner of a proposed recharge well or injection well must ensure that the person responsible constructs the well in accordance with
(a) the design of the proposed recharge well or injection well made by the professional under subsection (1) (b), and
(b) in the case of a proposed recharge well or injection well to which subsection (2) applies, the accepted design and the terms and conditions, if any, specified by the engineer under that subsection.
(5) The owner of a recharge well or injection well must
(a) ensure that the professional prepares as-built drawings of the well, and
(b) retain the design and any as-built drawings prepared by the professional until the well is decommissioned.
Read the Groundwater Protection Regulation on BC Laws ↗
Made under Water Sustainability Act, SBC 2014, c. 15.