Groundwater Protection Regulation, B.C. Reg. 39/2016
Section 18
Siting of water supply wells and permanent dewatering wells
Cite as Groundwater Protection Regulation, B.C. Reg. 39/2016, s. 18 · last amended December 1, 2022 · read from BC Laws on November 17, 2026
The text
(1) The person responsible for drilling a proposed water supply well or a proposed permanent dewatering well must site the proposed well so that the horizontal setback distance is not less than 15 m from any part of the proposed well to an existing water supply well, unless
(a) the existing water supply well is not in use and is not intended to be in use, or
(b) the owner of the proposed well also owns the existing water supply well and only one well is proposed to be drilled.
(2) The person responsible for drilling a proposed water supply well or proposed permanent dewatering well referred to in subsection (1) may, if the person responsible determines that it is not practicable to site the well as described in that subsection, site the proposed well with a horizontal setback distance from any part of the proposed well to an existing water supply well that is less than 15 m in accordance with alternative specifications that meet the requirements of subsection (3).
(3) A proposed well under subsection (2) may be sited in accordance with alternative specifications for the siting of the proposed well if
(a) a professional who has competency in the field of hydrogeology prepares the alternative specifications for the siting of the proposed well so that the existing uses of the existing water supply well will not be adversely affected,
(b) the person responsible for drilling the well submits the alternative specifications to an engineer for acceptance by the engineer before the proposed well is drilled,
(c) the engineer accepts the alternative specifications, with any terms and conditions the engineer may specify, and
(d) the person responsible drills the water supply well, or permanent dewatering well, in accordance with
(i) the alternative specifications accepted by the engineer under paragraph (c), and
(ii) the terms and conditions, if any, specified by the engineer under that paragraph.
(4) If a water supply well or permanent dewatering well is drilled in accordance with alternative specifications under subsection (3), the person responsible for drilling the well must include the accepted alternative specifications, including the terms and conditions specified by the engineer, if any, with the well construction report required under section 76 [well construction reports submitted to both comptroller and well owner].
Read the Groundwater Protection Regulation on BC Laws ↗
Made under Water Sustainability Act, SBC 2014, c. 15.