Landfill Gas Management Regulation, B.C. Reg. 391/2008
Section 8
Landfill gas management facilities
Cite as Landfill Gas Management Regulation, B.C. Reg. 391/2008, s. 8 · last amended March 30, 2022 · read from BC Laws on November 17, 2026
The text
(1) In this section, and in section 11, “accepted design plan” means a landfill gas management facilities design plan that has been accepted by the director under section 18.
(2) The owner or operator of a landfill site for which there is an accepted design plan must
(a) install landfill gas management facilities in accordance with the accepted design plan, and
(b) implement management practices, processes and methods for landfill gas management in accordance with any guidelines respecting
(i) migration of landfill gas,
(ii) use of landfill covers,
(iii) operation of landfill gas management facilities,
(iv) landfill gas collection equipment,
(v) landfill gas flaring equipment, and
(vi) landfill gas management facilities maintenance, including the number of days annually that landfill gas management facilities may be shut down.
(3) The landfill gas management facilities and practices referred to in subsection (2) must be installed and implemented no later than 4 years after the date the landfill gas management facilities design plan is submitted to the director under section 7.
(4) The owner or operator of a landfill site where landfill gas management facilities are installed must ensure that
(a) a qualified professional certifies in writing to the director that the facilities were installed in accordance with the accepted design plan for the landfill site, and
(b) the facilities are operated and maintained in accordance with the accepted design plan for the landfill site.
Read the Landfill Gas Management Regulation on BC Laws ↗
Made under Environmental Management Act, SBC 2003, c. 53.