(1) The owner or operator of a regulated landfill site that, as the result of an assessment conducted in accordance with this regulation, is estimated to generate 1 000 tonnes or more of methane in the calendar year immediately preceding the calendar year of the assessment must ensure that a landfill gas management facilities design plan is prepared for the landfill site.
(2) The plan required under this section must be prepared by a qualified professional in accordance with the guidelines and include the following information:
(a) a description of existing or planned methods, management practices and processes for landfill gas management at the landfill site;
(b) a plan for the installation, operation and maintenance of landfill gas management facilities at the landfill site, including a contingency plan for disruption in landfill gas management for scheduled or emergency maintenance or replacement of landfill gas management facilities;
(c) recommendations for optimizing landfill gas management at the landfill site;
(d) any other information required under the guidelines;
(e) any other information requested in writing by the director;
(f) certification by the qualified professional that the plan was prepared in accordance with the guidelines.
(3) The landfill gas management facilities design plan must be submitted to the director no later than one year after the date the report setting out the estimate was required to be submitted to the director.
(4) A landfill gas management facilities design plan that has been prepared for a landfill site before January 1, 2009 may be submitted to the director in substitution for the landfill gas management system design plan required under subsection (1) if a qualified professional certifies in writing that the landfill gas management system design plan prepared before January 1, 2009 meets the requirements set out in subsection (2).
(5) The owner or operator of a regulated landfill site that, as the result of an assessment conducted in accordance with this regulation, is estimated to generate less than 1 000 tonnes of methane gas in the calendar year immediately preceding the calendar year of the assessment may submit a plan to the director at any time.
Read the Landfill Gas Management Regulation on BC Laws ↗