Occupational Health and Safety Regulation, B.C. Reg. 296/97
Section 23.43
Ventilation openings
Cite as Occupational Health and Safety Regulation, B.C. Reg. 296/97, s. 23.43 · last amended September 1, 2027 · read from BC Laws on November 17, 2026
The text
(1) Before commencing drill stem tests, swabbing, bailing, or displacement with gas or oil
(a) derrick enclosures must be altered to provide openings at least 1.8 m (6 ft) high and 2.4 m (8 ft) wide on opposite sides above, and on 2 sides below, the derrick floor, or
(b) adequate mechanical ventilation or monitoring must be provided.
(2) If it is not practicable to provide openings as specified in subsection (1) (a), several openings must be made providing a total area of at least 4.5 sq m (50 sq ft) on each side.
(3) If mechanical ventilation is used
(a) it must be installed on the mud tank side,
(b) it must be able to completely change the air in the substructure every 2 minutes, and
(c) at least one opening must be provided in the front of the substructure to allow for adequate inflow of makeup air.
(4) During cold weather, ventilation procedures must not compromise the well control systems.
Read the Occupational Health and Safety Regulation on BC Laws ↗
Made under Workers Compensation Act, RSBC 2019, c. 1.