Occupational Health and Safety Regulation, B.C. Reg. 296/97

Section 21.88

Notice of project

Cite as Occupational Health and Safety Regulation, B.C. Reg. 296/97, s. 21.88 · last amended September 1, 2027 · read from BC Laws on November 17, 2026

The text

(1) The owner or the person engaged by the owner to be the prime contractor must ensure that the Board receives a written notice of project at least 24 hours before the beginning of a blasting operation that has an anticipated duration of 3 or more days. (2) Before blasting begins, a copy of the notice of project must be posted at the blast site.
Read the Occupational Health and Safety Regulation on BC Laws ↗

Made under Workers Compensation Act, RSBC 2019, c. 1.