Occupational Health and Safety Regulation, B.C. Reg. 296/97
Section 20.26.3
Standards
Cite as Occupational Health and Safety Regulation, B.C. Reg. 296/97, s. 20.26.3 · last amended September 1, 2027 · read from BC Laws on November 17, 2026
The text
(1) The operation, inspection, testing and maintenance of a concrete pump or placing boom manufactured before August 1, 2012 must meet the requirements of CSA Standard Z151-09, Concrete pumps and placing booms, as set out in clauses 1.1 to 3 [definitions], 4.1.9.2.3, 4.1.18.2, 4.1.19.1, 4.2.1.1, 4.2.2, 5.1.1 to 5.3.4, 5.3.7 to 6.3.4 and 6.5.1 to 6.7.3, including any table, figure or annex referred to in those clauses.
(2) The design, manufacture, installation, operation, inspection, testing and maintenance of a concrete pump or placing boom manufactured on or after August 1, 2012 must meet the requirements of CSA Standard Z151-09, Concrete pumps and placing booms, as set out in clauses 1.1 to 3 [definitions], 4.1.1.2 to 5.3.4, 5.3.7 to 6.3.4 and 6.5.1 to 6.7.3, including any table, figure or annex referred to in those clauses.
Read the Occupational Health and Safety Regulation on BC Laws ↗
Made under Workers Compensation Act, RSBC 2019, c. 1.