Occupational Health and Safety Regulation, B.C. Reg. 296/97
Section 14.42
Tandem lift
Cite as Occupational Health and Safety Regulation, B.C. Reg. 296/97, s. 14.42 · last amended September 1, 2027 · read from BC Laws on November 17, 2026
The text
(1) If a tandem lift is a critical lift or if the lifted load is to be moved laterally, the tandem lift must be carried out under the direction of a qualified supervisor who
(a) is not operating a crane, hoist or other piece of powered lifting equipment, and
(b) is responsible for the safe conduct of the operation.
(2) A written lift plan must be prepared for every tandem lift and must be available at the worksite during the lift.
(3) The lift plan required in subsection (2) must include the following:
(a) rigging details;
(b) wind speed limitations;
(c) maximum hoist line speed;
(d) maximum crane travel speed, if applicable;
(e) load distribution;
(f) the need for and position of signallers.
(4) If a tandem lift involves the use of a tower crane, the lift plan required in subsection (2) must be certified by a professional engineer.
(5) At a pre-job meeting held immediately before commencing hoisting operations for a tandem lift, the lift plan required in subsection (2) must be communicated to all people involved and the supervisor must document the meeting.
(6) The pre-job meeting required under subsection (5) must be repeated whenever there is a change in the people or equipment involved in the tandem lift.
(7) Effective communication must be established and maintained between all people involved in a tandem lift.
Read the Occupational Health and Safety Regulation on BC Laws ↗
Made under Workers Compensation Act, RSBC 2019, c. 1.