Renewable Energy Projects Regulation, B.C. Reg. 28/2026
Section 6
Invitation to consult
Cite as Renewable Energy Projects Regulation, B.C. Reg. 28/2026, s. 6 · last amended September 14, 2026 · read from BC Laws on November 17, 2026
The text
(1) An applicant in relation to a renewable energy project must, if required under section 22 (3), 31 (5) or 32 (3) of the Act, provide an invitation to consult to the following persons:
(a) the owner in fee simple of land within 1.5 km of the operating area or proposed operating area;
(b) a local authority, if a project area is within the geographic area of the local authority;
(c) a specified federal entity, if required by the regulator;
(d) a rights holder within the meaning of the Requirements for Consultation and Notification Regulation, B.C. Reg. 50/2021, if the criteria set out in section 7 (a) and (b) of that regulation are met.
(2) An invitation to consult must include the following information:
(a) a description of the project;
(b) if the invitation relates to an application under section 31 (5) of the Act for amendments, a description of the proposed amendments;
(c) the location of the project;
(d) the name and contact information of the person providing the invitation;
(e) a summary of the nature, geographic area and timing of the impacts on quality of life that would reasonably be expected to occur within 1.5 km of the operating area or proposed operating area;
(f) if the recipient is a local authority, a summary of the anticipated social and economic impacts of the project within the geographic area of the local authority.
(3) An invitation to consult must include the following statements:
(a) a statement advising that the recipient may, within 30 days after the date the recipient is deemed under section 79 (2) of the Act to have received the invitation, provide one or both of the following to the applicant:
(i) a written response stating whether the recipient has any concerns with the project, and, if so, the reasons for those concerns;
(ii) a written request for a meeting to discuss the project;
(b) if applicable, a statement advising that the recipient may make a submission to the regulator under section 22 (5) of the Act.
Read the Renewable Energy Projects Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.