Renewable Energy Projects Regulation, B.C. Reg. 28/2026

Section 5

Who must consult

Cite as Renewable Energy Projects Regulation, B.C. Reg. 28/2026, s. 5 · last amended September 14, 2026 · read from BC Laws on November 17, 2026

The text

(1) Persons who intend to submit an application under section 24 [application for permit] of the Act are prescribed for the purposes of section 22 (1) [consultation and notification]. (2) The notifications and consultations required by this Part are prescribed for the purposes of the following sections of the Act: (a) section 22 (3) [application for permit]; (b) section 31 (5) [amendment of permit]; (c) section 32 (3) [extension of permit].
Read the Renewable Energy Projects Regulation on BC Laws ↗

Made under Energy Resource Activities Act, SBC 2008, c. 36.