Drilling and Production Regulation, B.C. Reg. 282/2010
Section 67
Analysis of natural gas and hydrocarbon liquid production
Cite as Drilling and Production Regulation, B.C. Reg. 282/2010, s. 67 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) Subject to subsection (3), a well permit holder must take representative natural gas and hydrocarbon liquid samples from each producing formation from a well within 30 days of the initial production date.
(2) A well permit holder must submit to the regulator a report of the component analyses and physical properties of the natural gas and hydrocarbon liquids within 60 days of
(a) the sampling referred to in subsection (1), and
(b) any other natural gas sampling and analysis performed on the well.
(3) This section applies to hydrocarbon liquids only if produced from
(a) a zone listed in Schedule 2 and have a specific gravity of 0.8063 or less, or
(b) a zone not listed in Schedule 2 and have a specific gravity of 0.7796 or less.
Read the Drilling and Production Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.