Drilling and Production Regulation, B.C. Reg. 282/2010

Section 51

Storage and disposal of wastes

Cite as Drilling and Production Regulation, B.C. Reg. 282/2010, s. 51 · last amended April 1, 2025 · read from BC Laws on November 17, 2026

The text

(1) A well permit holder must ensure that formation water, oil, drilling fluid, completion fluid, waste, chemical substances or refuse from a well, tank or other facility do not do any of the following: (a) create a hazard to public health or safety; (b) run into or contaminate any water supply well, usable aquifer or water body or remain in a place from which it might contaminate any water supply well, usable aquifer or water body; (c) run over, pollute or damage any land or public road; (d) pass into or, on ice, over any water body that is frequented by fish or wildlife or that flows into any such water body. (2) A well permit holder who deposits into an earthen pit drilling fluids that may be harmful to domestic livestock or big game must maintain the pit so as to prevent, in a manner satisfactory to an official, domestic livestock or big game from ingesting the fluids. (3) A well permit holder who uses an earthen pit to store liquid waste from a well drilling operation must ensure that the pit is (a) not located within 100 m of the natural boundary of a water body, (b) not located within 200 m of a water supply well, (c) constructed of clay or other suitable impermeable material with the bottom of the pit above ground water level, (d) located or ditched so that it will not collect natural run-off water, (e) filled to not more than one metre below the point of overflow at any given time, and (f) completely emptied and any excavation filled without unreasonable delay. (4) Within 90 days of completing a drilling waste disposal, a well permit holder must submit to the regulator a report of the drilling waste disposal. (5) A well permit holder who uses an earthen pit to store water-based fluids that have a concentration of total dissolved solids greater than 4 000 ppm must (a) obtain a facility permit that authorizes the earthen pit, and (b) ensure that the earthen pit is designed by and installed under the supervision of a professional engineer licensed or registered under the Professional Governance Act. (6) A well permit holder who uses an above ground structure with a liner as the primary means of containment to store water-based fluids with a concentration of total dissolved solids greater than 4 000 ppm must ensure that (a) the fluids have been generated from or are being stored for the purpose of hydraulic fracturing operations, (b) the structure is not located within 100 m of the natural boundary of a water body unless the structure is on a permitted well location, (c) the capacity of each structure is not greater than 6 600 m3, (d) before the structure is used, a qualified professional verifies that contained fluids will not migrate beyond the lease boundary in the event of a complete containment failure, (e) the regulator is satisfied that the retaining walls of the structure are capable of withstanding the hydraulic pressure of the contents at full capacity, (f) the installation of the liner system is completed to the satisfaction of the regulator, (g) the ground surface has been prepared to the satisfaction of the regulator, (h) the structure is filled to not more than 50 cm below the point of overflow at any given time, (i) the structure is equipped with measures to prevent waterfowl from coming in contact with the fluids, (j) when the structure contains fluid, it is inspected daily for leaks and a record of inspection is maintained until the site is decommissioned, (k) any sign of leakage is reported to the regulator within 24 hours of discovery, and (l) the structure is decommissioned and removed from the site within one year from the date of first use unless there exists an engineered, lined or otherwise impermeable secondary containment system designed and maintained to be capable of holding a minimum of 110% of the fluid in the structure.
Read the Drilling and Production Regulation on BC Laws ↗

Made under Energy Resource Activities Act, SBC 2008, c. 36.