Drilling and Production Regulation, B.C. Reg. 282/2010
Section 29
Well samples and cores
Cite as Drilling and Production Regulation, B.C. Reg. 282/2010, s. 29 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) A well permit holder must
(a) unless paragraph (a.1) applies, take a series of drill cuttings samples at depth intervals of 5 m beginning at a point determined by the permit holder to be 50 m measured depth above the shallowest potential reservoir zone expected in the well and continuing to the total depth of the well,
(a.1) for horizontal wells drilled from a common drilling pad location and to be completed in a zone listed in Schedule 2, take drilling cutting samples as follows:
(i) for a minimum of one horizontal well on the pad location, at 5 m intervals beginning at a point determined by the permit holder to be 50 m measured depth above the shallowest potential reservoir zone expected in the well and continuing to the point at which the drilling of the horizontal portion of the well is begun;
(ii) for a minimum of one well on the pad location in each dominant direction of the horizontal portion of the well for each zone listed in Schedule 2, at 10 m intervals beginning at the point at which the drilling of the horizontal portion of the well is begun and continuing to the total depth of the well,
(b) collect, wash, dry, sort and preserve 2 complete sets of drill cuttings samples in vials, arranged in trays of adequate construction,
(c) clearly and accurately label the vials and trays with the name and location of the well and the sample depths represented and, if the well is a multi-leg well, identify the leg from which the cuttings originated, and
(d) deliver 2 sets of the drill cuttings samples, carriage prepaid, to the regulator not later than 14 days after the date of rig release.
(2) A well permit holder must
(a) as soon as practicable after collecting a core sample, remove the core sample from the core barrel and store it in book fashion in one or more core boxes,
(b) accurately label on the end of the box body, but not the box lid, the well permit number, the well name, the surface location of the well, the core number and interval and the length of the core recovered, and identify the top and bottom of the core on the core box,
(c) protect boxes containing the cores from theft, misplacement or exposure to the weather, and
(d) forward the core to the regulator, carriage prepaid, not later than 14 days after the date of rig release.
(3) A well permit holder must ensure that core boxes are of adequate construction, the sides of the boxes project above the level of the contained cores, lids are securely fixed to ensure safe transit and the boxes have an inside length of 80 cm.
(4) When submitting a core that has been slabbed, a well permit holder must ensure that the 1/3 slab is either placed in the core box with the corresponding 2/3 slab, or, with the approval of an official, preserved as a viewing slab and submitted in cardboard boxes of adequate construction.
Read the Drilling and Production Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.