Drilling and Production Regulation, B.C. Reg. 282/2010
Section 25
Inactive or suspended wells
Cite as Drilling and Production Regulation, B.C. Reg. 282/2010, s. 25 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) In this section:
“active” means
(a) production, injection or disposal of fluids,
(b) drilling or completion operations, and
(c) with respect to a well designated under section 2 (7), monitoring reservoir pressure or obtaining other formation information;
“inactive”, in relation to a well, means a well that has not been abandoned but
(a) has not been active for 12 consecutive months, or
(b) if the well is classified as a special sour well, has not been active for 6 consecutive months.
(2) The well permit holder of an inactive well must submit a report to the regulator within 30 days of the suspension of a well.
(3) The well permit holder of a suspended well must establish a program of inspections sufficient to ensure the ongoing integrity of the well.
(4) The well permit holder of a suspended well must maintain records of the inspections referred to in subsection (3).
(5) The well permit holder of an inactive well, within 60 days of the well becoming inactive, must do both of the following:
(a) suspend the well in a manner that ensures the ongoing integrity of the well;
(b) ensure positive isolation between the well and the flowline by disconnecting the well from the flowline or by other means.
Read the Drilling and Production Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.