Pipeline Regulation, B.C. Reg. 281/2010
Section 5
Requirements after construction of pipeline
Cite as Pipeline Regulation, B.C. Reg. 281/2010, s. 5 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) Before beginning operation of a pipeline, a pipeline permit holder must do all of the following:
(a) test the pipeline in accordance with CSA Z662, or the codes or standards referred to in section 2 (c), as applicable;
(b) inspect and test all control and safety devices to ensure that the devices are in good working order;
(c) take any other steps reasonably necessary to ensure that the pipeline is safe for use.
(2) A pipeline permit holder must restore, in accordance with subsection (3), the surface of the land disturbed by the construction of a pipeline by
(a) removing all structures installed to facilitate construction and not required for the operation of the pipeline, and
(b) stabilizing, contouring, conditioning or reconstructing the surface of the land to the extent reasonable in the circumstances.
(3) Restoration work under subsection (2) must be carried out
(a) as soon as practicable, considering, without limitation, weather and ground conditions, while construction of the pipeline is underway, and,
(b) with respect to any restoration work not completed when construction of the pipeline is completed, as soon as practicable after construction of the pipeline is completed.
(4) A pipeline permit holder must ensure that, after the pipeline is constructed, the right of way is kept free of garbage, debris and derelict equipment.
Read the Pipeline Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.