Pipeline Regulation, B.C. Reg. 281/2010
Section 4
Notices and other submissions
Cite as Pipeline Regulation, B.C. Reg. 281/2010, s. 4 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) A pipeline permit holder must notify the regulator
(a) at least 2 days before beginning construction of a pipeline of its intention to begin construction,
(b) at least 2 days before beginning a pressure test of a pipeline of its intention to begin testing, and
(c) before beginning operation of a pipeline of its intention to begin operation.
(2) Within 60 days after a pipeline permit holder completes construction of the pipeline and all associated activities, the holder must prepare and submit to the regulator post-construction plot plans showing the location of the pipeline and all associated energy resource activities.
(3) Within 90 days after a pipeline permit holder completes construction of or any permitted modifications to the pipeline, the holder must
(a) prepare record drawings,
(b) have the record drawings signed and sealed by a professional engineer, and
(c) submit to the regulator
(i) the record drawings, and
(ii) the pipe and component specifications.
Read the Pipeline Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.