The text
(1) A hydrogen facility permit holder must not vent gas from the hydrogen facility unless the gas heating value, volume or flow rate is insufficient to support stable combustion.
(2) A hydrogen facility permit holder must not flare gas from the hydrogen facility unless permission to flare is included in the hydrogen facility permit.
(3) If venting or flaring occurs, a hydrogen facility permit holder must
(a) minimize the quantity of vented or flared gas and the duration of venting or flaring, and
(b) ensure that emissions from vents or flares do not cause
(i) a material threat to life or health,
(ii) off-site odours, or
(iii) injury to vegetation or wildlife.
(4) A hydrogen facility permit holder must ensure that ignitable vent stacks and flares are sited so that the thermal radiation flux at the locations identified in column 1 of the applicable table in Schedule 1 does not exceed the maximum thermal radiation flux identified opposite those locations in column 2 of that table.