Hydrogen Facility Regulation, B.C. Reg. 27/2025

Section 12

Hydrogen facility general requirements

Cite as Hydrogen Facility Regulation, B.C. Reg. 27/2025, s. 12 · last amended March 10, 2026 · read from BC Laws on November 17, 2026

The text

(1) Subject to section 3 (3) and any exemption granted under section 47, a hydrogen facility permit holder must ensure that the design, siting, construction, operation, suspension and decommissioning of the hydrogen facility (a) are consistent with the information and records given to the regulator under section 11, (b) comply with the codes and standards, and (c) are consistent with generally accepted good engineering practices. (2) A hydrogen facility permit holder must ensure that the hydrogen facility is constructed and operated (a) in accordance with the design, and (b) without causing excessive noise or light.
Read the Hydrogen Facility Regulation on BC Laws ↗

Made under Energy Resource Activities Act, SBC 2008, c. 36.