Energy Resource Activities General Regulation, B.C. Reg. 274/2010
Section 25
Well site survey
Cite as Energy Resource Activities General Regulation, B.C. Reg. 274/2010, s. 25 · last amended July 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) Within 90 days after receiving a well permit, a well permit holder must
(a) complete a well site survey and well site survey plan for the permitted well in accordance with the applicable rules made under section 75 of the Land Surveyors Act, and
(b) submit, in a form acceptable to the Surveyor General, the well site survey plan to the Surveyor General.
(2) On submission of a well site survey plan under subsection (1), the Surveyor General may confirm that the well site survey and well site survey plan were made in compliance with subsection (1) (a) and file the well site survey plan in the Crown land registry.
(3) If the location of the well shown on a well site survey plan is changed or a new well is drilled on the well site after the well site survey plan is submitted to the Surveyor General under subsection (1), the well permit holder must submit, within 90 days of the change of location or the drilling of the new well, a revised well site survey plan to the Surveyor General and subsections (1) (a) and (2) apply to that submission.
Read the Energy Resource Activities General Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.