Energy Resource Activities General Regulation, B.C. Reg. 274/2010
Section 24
Pipeline survey
Cite as Energy Resource Activities General Regulation, B.C. Reg. 274/2010, s. 24 · last amended July 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) Within 16 months after completion of a pipeline, a pipeline permit holder must do the following:
(a) complete the surveying and posting of the pipeline right of way according to applicable rules made under section 75 of the Land Surveyors Act;
(b) if the pipeline or a portion of the pipeline goes through Crown land, submit to the regulator the plans of the survey through Crown land;
(c) if the pipeline or a portion of the pipeline goes through land other than Crown land, submit to the registrar under the Land Title Act for deposit the plans of the survey through land other than Crown land in the form required under that Act.
(2) The regulator may issue to a pipeline permit holder who submitted plans under subsection (1) (b) an approval of the plans if the regulator is satisfied the plans represent a pipeline approved by the pipeline permit holder's permit.
(3) Within 30 days of receiving an approval under subsection (2), a pipeline permit holder must submit to the Surveyor General the approved plans in the form required under the rules referred to in subsection (1) (a).
(4) After approval by the Surveyor General, the plans of Crown land required under subsection (1) (b) are the official plans of survey of the right of way through Crown land.
Read the Energy Resource Activities General Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.