(1) Despite section 3, a new project and a modification of an existing project are prescribed as a reviewable project if the project is in a category listed in Column 1 of an applicable table and meets any of the following thresholds:
(a) emits 380 000 tonnes or more per year of one or more greenhouse gases directly from project facilities, measured in carbon dioxide equivalents, determined in accordance with Part 3 of the Greenhouse Gas Emission Reporting Regulation, B.C. Reg. 249/2015;
(b) includes one or more facilities located, in whole or in part, in an area listed in the Protected Areas (Environmental Assessment Act) Regulation and the project will have a significant adverse environmental, economic, social, cultural or health effect in the area;
(c) includes the clearance of
(i) 60 km or more of land that is to be developed for a transmission line, transmission pipeline, railway, public highway or resource road, if the land is not alongside and contiguous to an area of land previously developed for one of those purposes, or
(ii) 600 ha or more of land, unless the clearance has been authorized by the minister, or delegate, under the Resort Timber Administration Act.
(2) Subsection (1) (b) does not apply to a portion of a project that
(a) is in the area listed in the Protected Areas (Environmental Assessment Act) Regulation, and
(b) has, on the date this section comes into force, an authorization under an enactment listed in that regulation.
(3) Subsection (1) (c) does not apply to the following project categories described in Column 1 of the applicable tables:
(a) transmission lines;
(b) transmission pipelines;
(c) public highways;
(d) railways.