Timber Harvesting Contract and Subcontract Regulation, B.C. Reg. 22/96
Section 33.2
Forestry revitalization proposals
Cite as Timber Harvesting Contract and Subcontract Regulation, B.C. Reg. 22/96, s. 33.2 · last amended March 30, 2022 · read from BC Laws on November 17, 2026
The text
(1) Subject to subsection (4), after receipt of an order from the minister under section 3 (2) of the Forestry Revitalization Act for a group of licences, or after June 21, 2004 for an ungrouped licence, a licence holder may make one or more forestry revitalization proposals regarding the replaceable contracts pertaining to those licences to
(a) vary the amount of work specified in, or to terminate, one or more of those replaceable contracts, or
(b) change a contract such that it pertains to a different licence.
(2) The minister may, by order, specify the date by which a licence holder must make a forestry revitalization proposal under subsection (1).
(3) A licence holder must not make a forestry revitalization proposal, other than an amended proposal, after the time specified in the order from the minister under subsection (2).
(4) Subject to subsection (5), a licence holder must not include a licence in a forestry revitalization proposal, other than an amendment of a proposal that included that licence, if
(a) the licence was included in a previous forestry revitalization proposal, or
(b) the licence has been subject to a proportionate reduction under section 33.6.
(5) Despite subsection (4), the licence holder may include a licence in more than one forestry revitalization proposal if
(a) the licence was included in an order under section 3 of the Forestry Revitalization Act and was either included in a forestry revitalization proposal or was subject to proportionate reduction under section 33.6, and
(b) the licence holder receives a subsequent order from the minister under section 3 of the Forestry Revitalization Act in respect of that licence.
(6) A forestry revitalization proposal may include licences from the coastal area or licences from the interior area, but not both.
Read the Timber Harvesting Contract and Subcontract Regulation on BC Laws ↗
Made under Forest Act, RSBC 1996, c. 157.